A. The following permit revisions are administrative permit amendments for affected units:
1. Activation of a compliance option
conditionally approved by the department, provided that all requirements for
activation under
9VAC5-80-450
C and
9VAC5-80-460
are met.
2. Changes in the
designated representative or alternative designated representative, provided
that a new certificate of representation is submitted to the administrator in
accordance with Subpart B of 40 CFR Part 72.
3. Correction of typographical
errors.
4. Changes in names,
addresses, or telephone or facsimile numbers.
5. Changes in the owners or operators,
provided that a new certificate of representation is submitted within 30 days
to the administrator in accordance with Subpart B of 40 CFR Part 72.
6. Termination of a compliance option in the
permit, provided that all requirements for termination under
9VAC5-80-450
D shall be met and this procedure shall not be used to terminate a repowering
plan after December 31, 1999.
7.
Changes in the date, specified in a new unit's acid rain permit, of
commencement of operation or the deadline for monitor certification, provided
that they are in accordance with
9VAC5-80-420.
8. The addition of or change in a nitrogen
oxides alternative emissions limitation demonstration period, provided that the
requirements of the 40 CFR Part 76 are met.
9. The addition of a
NOX early election plan that was approved by the
administrator under
40 CFR
76.8.
10. The addition of an exemption for which
the requirements have been met under
40 CFR 72.7
or 40 CFR 72.8 or which was approved
by the department; and
11.
Incorporation of changes that the administrator has determined to be similar to
those in subdivisions 1 through 8 of this subsection.
B. The following provisions shall apply:
1. The department shall take final action on
an administrative permit amendment within 60 days, or, for the addition of an
alternative emissions limitation demonstration period, within 90 days, of
receipt of the requested amendment and may take such action without providing
prior public notice. The source may implement any changes in the administrative
permit amendment immediately upon submission of the requested amendment,
provided that the requirements of subsection A of this section are
met.
2. The department may, on its
own motion, make an administrative permit amendment at least 30 days after
providing notice to the designated representative of the amendment and without
providing any other prior public notice.
3. The department shall designate the permit
revision as having been made as an administrative permit amendment. The
department shall submit the revised portion of the permit to the
administrator.
4. An administrative
amendment shall not be subject to the provisions for review by the
administrator applicable to a permit modification under
40 CFR
72.81.
Statutory Authority: § 10.1-1308 of the Code of Virginia.
Disclaimer: These regulations may not be the most recent version. Virginia may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google
Privacy Policy and
Terms of Service apply.