A.
General information applies as follows:
1. For
major sources subject to this article, the department shall include in the
permit all applicable requirements for all emissions units in the major
source.
2. For any source other
than a major source subject to this article, the department shall include in
the permit all applicable requirements that apply to emissions units that cause
the source to be subject to this article.
3. For all sources subject to this article,
the department shall include in the permit applicable requirements that apply
to fugitive emissions regardless of whether the source category in question is
included in the list of sources contained in the definition of major
source.
4. Each permit issued under
this article shall include the elements listed in subsections B through N of
this section.
B. Each
permit shall contain terms and conditions setting out the following
requirements with respect to emission limitations and standards:
1. The permit shall specify and reference
applicable emission limitations and standards, including those operational
requirements and limitations that assure compliance with all applicable
requirements at the time of permit issuance.
2. The permit shall specify and reference the
origin of and authority for each term or condition and shall identify any
difference in form as compared to the applicable requirement upon which the
term or condition is based.
3. If
applicable requirements contained in the Regulations for the Control and
Abatement of Air Pollution allow a determination of an alternative emission
limit at a source, equivalent to that contained in the Regulations for the
Control and Abatement of Air Pollution, to be made in the permit issuance,
renewal, or significant modification process, any permit containing such
equivalency determination shall contain provisions to ensure that any resulting
emissions limit has been demonstrated to be quantifiable, accountable,
enforceable, and based on replicable procedures.
C. Each permit shall contain terms and
conditions identifying equipment specifications and operating parameters in
accordance with the following:
1. Each permit
shall contain terms and conditions setting out the following elements
identifying equipment specifications and operating parameters:
a. Specifications for permitted equipment,
identified as thoroughly as possible. The identification shall include, but not
be limited to, type, rated capacity, and size.
b. Specifications for air pollution control
equipment installed or to be installed.
c. Specifications for air pollution control
equipment operating parameters and the circumstances under which such equipment
shall be operated, where necessary to ensure that the required overall control
efficiency is achieved.
2. The information on any specification
required in subdivisions 1 a and b of this subsection may be included in the
permit for informational purposes only and does not form an enforceable term or
condition of the permit except in the following cases:
a. The specification is an applicable federal
requirement.
b. The specification
is derived from and necessary to enforce an applicable federal
requirement.
c. The operation of
the source contrary to the specification would violate an applicable federal
requirement.
d. The owner
voluntarily takes the specification as a state enforceable term or condition of
the permit pursuant to
9VAC5-80-300.
D. Each permit shall
contain a condition setting out the expiration date, reflecting a fixed term of
five years.
E. Each permit shall
contain terms and conditions setting out the following requirements with
respect to monitoring:
1. All emissions
monitoring and analysis procedures or test methods required under the
applicable monitoring and testing requirements, including 40 CFR Part 64 and
any other procedures and methods promulgated pursuant to § 504(b) or
§ 114(a)(3) of the federal Clean Air Act concerning compliance monitoring,
including enhanced compliance monitoring. If more than one monitoring or
testing requirement applies, the permit may specify a streamlined set of
monitoring or testing provisions provided the specific monitoring or testing is
adequate to assure compliance at least to the same extent as the applicable
requirements relating to monitoring or testing that are not included in the
permit as a result of such streamlining.
2. Where the applicable requirement does not
require periodic testing or instrumental or noninstrumental monitoring (which
may consist of recordkeeping designed to serve as monitoring), periodic
monitoring sufficient to yield reliable data from the relevant time period that
are representative of the source's compliance with the permit, as reported
pursuant to subdivision F 1 a of this section. Such monitoring requirements
shall assure use of terms, test methods, units, averaging periods, and other
statistical conventions consistent with the applicable requirement.
Recordkeeping provisions may be sufficient to meet the requirements of this
subdivision.
3. As necessary,
requirements concerning the use, maintenance, and, where appropriate,
installation of monitoring equipment or methods.
F. Recordkeeping and reporting requirements
apply as follows:
1. To meet the requirements
of subsection E of this section with respect to recordkeeping, the permit shall
contain terms and conditions setting out all applicable recordkeeping
requirements and requiring, where applicable, the following:
a. Records of monitoring information that
include the following:
(1) The date, place as
defined in the permit, and time of sampling or measurements.
(2) The dates analyses were
performed.
(3) The company or
entity that performed the analyses.
(4) The analytical techniques or methods
used.
(5) The results of such
analyses.
(6) The operating
conditions existing at the time of sampling or measurement.
b. Retention of records of all
monitoring data and support information for at least five years from the date
of the monitoring sample, measurement, report, or application. Support
information includes all calibration and maintenance records and all original
strip-chart recordings for continuous monitoring instrumentation, and copies of
all reports required by the permit.
2. To meet the requirements of subsection E
of this section with respect to reporting, the permit shall contain terms and
conditions setting out all applicable reporting requirements and requiring the
following:
a. Submittal of reports of any
required monitoring at least every six months. All instances of deviations from
permit requirements must be clearly identified in such reports. All required
reports must be certified by a responsible official consistent with
9VAC5-80-80
G.
b. Prompt reporting of
deviations from permit requirements, including those attributable to upset
conditions as defined in the permit, the probable cause of such deviations, and
any corrective actions or preventive measures taken. The department shall
define "prompt" in the permit condition in relation to (i) the degree and type
of deviation likely to occur and (ii) the applicable requirements.
G. Each permit shall
contain terms and conditions with respect to enforcement that state the
following:
1. If any condition, requirement or
portion of the permit is held invalid or inapplicable under any circumstance,
such invalidity or inapplicability shall not affect or impair the remaining
conditions, requirements, or portions of the permit.
2. The permittee shall comply with all
conditions of the permit. Any permit noncompliance constitutes a violation of
the federal Clean Air Act or the Virginia Air Pollution Control Law or both and
is grounds for enforcement action; for permit termination, revocation and
reissuance, or modification; or for denial of a permit renewal
application.
3. It shall not be a
defense for a permittee in an enforcement action that it would have been
necessary to halt or reduce the permitted activity in order to maintain
compliance with the conditions of this permit.
4. The permit may be modified, revoked,
reopened, and reissued, or terminated for cause as specified in subsection L of
this section,
9VAC5-80-240
and
9VAC5-80-260. The
filing of a request by the permittee for a permit modification, revocation and
reissuance, or termination, or of a notification of planned changes or
anticipated noncompliance does not stay any permit condition.
5. The permit does not convey any property
rights of any sort, or any exclusive privilege.
6. The permittee shall furnish to the
department, within a reasonable time, any information that the department may
request in writing to determine whether cause exists for modifying, revoking
and reissuing, or terminating the permit or to determine compliance with the
permit. Upon request, the permittee shall also furnish to the department copies
of records required to be kept by the permit and, for information claimed to be
confidential, the permittee shall furnish such records to the department along
with a claim of confidentiality.
H. Each permit shall contain a condition
setting out the requirement to pay permit fees consistent with the fee schedule
approved pursuant to Article 2 (9VAC5-80-310 et
seq.) of this part.
I. Emissions
trading information as follows shall be included:
1. Each permit shall contain a condition with
respect to emissions trading that states the following:
No permit revision shall be required, under any approved
economic incentives, marketable permits, emissions trading and other similar
programs or processes for changes that are provided for in the permit.
2. Each permit shall contain the
following terms and conditions, if the permit applicant requests them, for the
trading of emissions increases and decreases within the permitted facility, to
the extent that the Regulations for the Control and Abatement of Air Pollution
provide for trading such increases and decreases without a case-by-case
approval of each emissions trade:
a. All terms
and conditions required under this section except subsection N of this section
shall be included to determine compliance.
b. The permit shield described in
9VAC5-80-140 shall
extend to all terms and conditions that allow such increases and decreases in
emissions.
c. The owner shall meet
all applicable requirements including the requirements of this
article.
J.
Each permit shall contain terms and conditions setting out requirements with
respect to reasonably anticipated operating scenarios when identified by the
source in its application and approved by the department. Such requirements
shall include but not be limited to the following:
1. Contemporaneously with making a change
from one operating scenario to another, the source shall record in a log at the
permitted facility a record of the scenario under which it is
operating.
2. The permit shield
described in
9VAC5-80-140 shall
extend to all terms and conditions under each such operating
scenario.
3. The terms and
conditions of each such alternative scenario shall meet all applicable
requirements including the requirements of this article.
K. Consistent with subsections E and F of
this section, each permit shall contain terms and conditions setting out the
following requirements with respect to compliance:
1. Compliance certification, testing,
monitoring, reporting, and recordkeeping requirements sufficient to assure
compliance with the terms and conditions of the permit. Any document (including
reports) required in a permit condition to be submitted to the department shall
contain a certification by a responsible official that meets the requirements
of
9VAC5-80-80
G.
2. Inspection and entry
requirements that require that, upon presentation of credentials and other
documents as may be required by law, the owner shall allow the department to
perform the following:
a. Enter upon the
premises where the source is located or emissions-related activity is
conducted, or where records must be kept under the terms and conditions of the
permit.
b. Have access to and copy,
at reasonable times, any records that must be kept under the terms and
conditions of the permit.
c.
Inspect at reasonable times any facilities, equipment (including monitoring and
air pollution control equipment), practices, or operations regulated or
required under the permit.
d.
Sample or monitor at reasonable times substances or parameters for the purpose
of assuring compliance with the permit or applicable requirements.
3. A schedule of compliance
consistent with
9VAC5-80-90
I.
4. Progress reports consistent
with an applicable schedule of compliance and
9VAC5-80-90
I to be submitted at least semiannually, or at a more frequent period if
specified in the applicable requirement or by the department. Such progress
reports shall contain the following:
a. Dates
for achieving the activities, milestones, or compliance required in the
schedule of compliance, and dates when such activities, milestones or
compliance were achieved.
b. An
explanation of why any dates in the schedule of compliance were not or will not
be met, and any preventive or corrective measures adopted.
5. Requirements for compliance certification
with terms and conditions contained in the permit, including emission
limitations, standards, or work practices. Permits shall include each of the
following:
a. The frequency (not less than
annually or such more frequent periods as specified in the applicable
requirement or by the department) of submissions of compliance
certifications.
b. In accordance
with subsection E of this section, a means for assessing or monitoring the
compliance of the source with its emissions limitations, standards, and work
practices.
c. A requirement that
the compliance certification include the following (provided that the
identification of applicable information may cross-reference the permit or
previous reports, as applicable):
(1) The
identification of each term or condition of the permit that is the basis of the
certification.
(2) The
identification of the methods or other means used by the owner or operator for
determining the compliance status with each term and condition during the
certification period, and whether such methods or other means provide
continuous or intermittent data. Such methods and other means shall include, at
a minimum, the methods and means required under subsection E of this section.
If necessary, the owner or operator shall also identify any other material
information that must be included in the certification to comply with §
113(c)(2) of the federal Clean Air Act, which prohibits knowingly making a
false certification or omitting material information.
(3) The status of compliance with the terms
and conditions of the permit for the period covered by the certification, based
on the method or means designated in subdivision 5 c (2) of this subsection.
The certification shall identify each deviation and take it into account in the
compliance certification. The certification shall also identify as possible
exceptions to compliance any periods during which compliance is required and in
which an excursion or exceedance as defined under 40 CFR Part 64
occurred.
(4) Such other facts as
the department may require to determine the compliance status of the
source.
d. All compliance
certifications shall be submitted by the permittee to the administrator as well
as to the department.
6.
Such other provisions as the department may require.
L. Each permit shall contain terms and
conditions setting out the following requirements with respect to reopening the
permit prior to expiration:
1. The permit
shall be reopened by the department if additional applicable federal
requirements become applicable to a major source with a remaining permit term
of three or more years. Such a reopening shall be completed not later than 18
months after promulgation of the applicable requirement. No such reopening is
required if the effective date of the requirement is later than the date on
which the permit is due to expire, unless the original permit or any of its
terms and conditions has been extended pursuant to
9VAC5-80-80
F.
2. The permit shall be reopened
if the department or the administrator determines that the permit contains a
material mistake or that inaccurate statements were made in establishing the
emissions standards or other terms or conditions of the permit.
3. The permit shall be reopened if the
administrator or the department determines that the permit must be revised or
revoked to assure compliance with the applicable requirements.
4. The permit shall not be reopened by the
department if additional applicable state requirements become applicable to a
major source prior to the expiration date established under subsection D of
this section.
M. The
permit shall contain terms and conditions pertaining to other requirements as
may be necessary to ensure compliance with the Regulations for the Control and
Abatement of Air Pollution, the Virginia Air Pollution Control Law and the
federal Clean Air Act.
N. Federal
enforceability requirements apply as follows:
1. All terms and conditions in a permit,
including any provisions designed to limit a source's potential to emit, are
enforceable by the administrator and citizens under the federal Clean Air Act,
except as provided in subdivision 2 of this subsection.
2. The department shall specifically
designate as being only state-enforceable any terms and conditions included in
the permit that are not required under the federal Clean Air Act or under any
of its applicable federal requirements. Terms and conditions so designated are
not subject to the requirements of
9VAC5-80-290
concerning review of proposed permits by EPA and draft permits by affected
states.
3. The department may
specifically designate as state enforceable any applicable state requirement
that has been submitted to the administrator for review to be approved as part
of the implementation plan and that has not yet been approved. The permit shall
specify that the provisions will become federally enforceable upon approval of
the provisions by the administrator and through an administrative permit
amendment.
Statutory Authority: § 10.1-1308 of the Code of
Virginia.