Virginia Administrative Code
Title 9 - ENVIRONMENT
Agency 5 - STATE AIR POLLUTION CONTROL BOARD
Chapter 60 - HAZARDOUS AIR POLLUTANT SOURCES
Part II - Emission Standards
Article 3 - Control Technology Determinations for Major Sources of Hazardous Air Pollutants(Rule 6-3)
Section 9VAC5-60-160 - Preconstruction review procedures for new affected sources subject to 9VAC5-60-140 C 1
Current through Register Vol. 41, No. 3, September 23, 2024
A. The review process for new affected sources is as follows:
B. The board will provide for an enhanced review of MNSR permits used to implement case-by-case MACT determinations in accordance with the following review procedures and compliance requirements:
C. The board will provide opportunity for public comment on the preliminary MNSR permit prior to issuance, including, at a minimum:
D. The board will send copies of the preliminary permit (in time for comment) and final permit required by subsection C of this section to the administrator through the appropriate regional office, to affected states, and to all other state and local air pollution control agencies having jurisdiction in the region in which the new source would be located. The board will provide EPA with a review period for the final permit of at least 45 days, and will not issue the final MNSR permit until EPA objections are satisfied.
E. An owner of a major source that is subject to a case-by-case MACT determination shall comply with notification, operation and maintenance, performance testing, monitoring, reporting, and recordkeeping requirements established under 9VAC5-60-140 F 2, under the federal operating permit program, and at the discretion of the board, under Subpart A of 40 CFR Part 63. The board will provide the EPA with the opportunity to review compliance requirements for consistency with requirements established pursuant to the federal operating permit program during the review period under subsection D of this section.
F. If the board requires a new source review permit for a new source case-by-case MACT determination under this article, such requirement will not necessitate a determination under Subpart E of 40 CFR Part 63.
Statutory Authority
§ 10.1-1308 of the Code of Virginia, § 112 of the Clean Air Act, and 40 CFR Parts 61 and 63.