The owner shall furnish written notification to the regional office of the following:

1. The actual date on which construction or modification of each affected unit commenced within 30 days after such date.

2. If necessary, the actual date on which the integration operational period of each affected unit commenced within 15 days after such date.

3. The anticipated start-up date of each affected unit postmarked or submitted electronically not more than 60 days nor less than 30 days prior to such date.

4. The actual start-up date of each affected unit within 15 days after such date.

Statutory Authority: § 10.1-1308 of the Code of Virginia.

Disclaimer: These regulations may not be the most recent version. Virginia may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.