Virginia Administrative Code
Title 9 - ENVIRONMENT
Agency 5 - STATE AIR POLLUTION CONTROL BOARD
Chapter 540 - EMERGENCY GENERATOR GENERAL PERMIT
Part IV - General Permit Terms and Conditions
Section 9VAC5-540-210 - Reporting requirements
Current through Register Vol. 41, No. 3, September 23, 2024
The owner shall furnish written notification to the regional office of the following:
1. The actual date on which construction or modification of each affected unit commenced within 30 days after such date.
2. If necessary, the actual date on which the integration operational period of each affected unit commenced within 15 days after such date.
3. The anticipated start-up date of each affected unit postmarked or submitted electronically not more than 60 days nor less than 30 days prior to such date.
4. The actual start-up date of each affected unit within 15 days after such date.
Statutory Authority: § 10.1-1308 of the Code of Virginia.