Virginia Administrative Code
Title 9 - ENVIRONMENT
Agency 5 - STATE AIR POLLUTION CONTROL BOARD
Chapter 530 - ELECTRIC GENERATOR VOLUNTARY DEMAND RESPONSE GENERAL PERMIT
Part V - General Permit Terms and Conditions for Electric Generating Units Using Hoursof Operation for Compliance Demonstration
Section 9VAC5-530-250 - Operating limits
Current through Register Vol. 41, No. 3, September 23, 2024
A. The approved fuels for each CI affected unit are diesel fuel, biodiesel fuel, and biodiesel blends. These fuels shall meet the following specifications:
B. The approved fuels for each SI affected unit are natural gas and liquid petroleum gas (LPG). These fuels shall meet the following specifications.
C. Each affected unit shall not operate more than 350 hours per year, calculated monthly as the sum of each consecutive 12-month period.
D. For affected units using diesel fuel or biodiesel fuel the owner shall obtain a certification from the fuel supplier with each shipment of diesel fuel or biodiesel fuel. Each fuel supplier certification shall include the following:
Statutory Authority
§§ 10.1-1307.02 and 10.1-1308 of the Code of Virginia.