A. The permittee shall comply with the reporting requirements in this section. Any document (including reports) required by a permit term or condition to be submitted to the department shall contain a document certification signed by a responsible official that meets the requirements of 9VAC5-20-230.
B. The permittee shall furnish written notification to the department of the following dates relative to the requirements of 9VAC5-520-180:
1. The actual date on which construction or
installation of any biomass pilot test facility commenced, postmarked within 30
days after that date;
2. The
anticipated startup date of the biomass pilot test facility, postmarked not
more than 60 days nor less than 30 days prior to such date;
3. The actual startup date of the biomass
pilot test facility postmarked within 15 days after that date;
4. The test protocol, postmarked at least 30
days prior to the date that testing commences; and
5. The test results, no later than 45 days
after test completion of the stack tests and visible emissions
evaluation.
Statutory Authority
§ 10.1-1308.1 of the Code of Virginia; § 110(a) of the federal Clean Air Act; 40 CFR Part 51.
Disclaimer: These regulations may not be the most recent version. Virginia may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google
Privacy Policy and
Terms of Service apply.