A. Deadlines for
submitting registration statement. Any operator seeking coverage under this
general permit, and that is required to submit a registration statement, shall
submit a complete and accurate general VPDES permit registration statement in
accordance with this section, which shall serve as a notice of intent for
coverage under the general VPDES permit for discharges of stormwater from
construction activities.
1. New construction
activities.
a. Any operator proposing a new
stormwater discharge from construction activities shall submit a complete and
accurate registration statement to the VESMP authority prior to the
commencement of land disturbance.
b. Any operator proposing a new stormwater
discharge from construction activities in response to a public emergency where
the related work requires immediate authorization to avoid imminent
endangerment to human health or the environment is authorized to discharge
under this general permit, provided that:
(1)
The operator submits a complete and accurate registration statement to the
VESMP authority no later than 30 days after the commencement of land
disturbance; and
(2) Documentation
to substantiate the occurrence of the public emergency is provided with the
registration statement.
c. Any operator proposing a new stormwater
discharge associated with a small construction activity involving the
construction of a single-family detached residential structure, within or
outside a common plan of development or sale, is authorized to discharge under
this general permit and is not required to submit a registration statement. Any
operator proposing a new stormwater discharge associated with the construction
of a single-family detached residential structure, within or outside a common
plan of development or sale, is not required to submit the department portion
of the permit fee.
2.
Existing construction activities.
a. Any
operator who was authorized to discharge under the expiring or expired 2019
general permit and who intends to continue coverage under this general permit
shall:
(1) Submit a complete and accurate
registration statement to the VESMP authority at least 90 days prior to the
expiration date of the existing permit or a later submittal date established by
the department; and
(2) Update its
stormwater pollution prevention plan to comply with the requirements of this
general permit no later than 60 days after the date of coverage under this
general permit.
b. Any
operator with an existing stormwater discharge associated with a small
construction activity involving the construction of a single-family detached
residential structure, within or outside a common plan of development or sale,
that intends to continue coverage under this general permit, is authorized to
discharge under this general permit and is not required to submit a
registration statement, provided that the operator updates its stormwater
pollution prevention plan to comply with the requirements of this general
permit no later than 60 days after the date of coverage under this general
permit. Any operator with an existing stormwater discharge associated with the
construction of a single-family detached residential structure, within or
outside a common plan of development or sale, that intends to continue coverage
under this general permit is not required to submit the department portion of
the permit fee.
3.
Transfer of ownership. The new operator shall submit a complete and accurate
registration statement or transfer of ownership agreement form and any other
documents required by the VESMP authority to the VESMP authority prior to
assuming operational control over construction site specifications or the
commencement of land disturbance.
4. Late submissions. Operators are not
prohibited from submitting registration statements after the commencement of
land disturbance. When a late registration statement is submitted,
authorization for discharges shall not occur until coverage under the general
permit is issued. The VESMP authority, department, and EPA reserve the right to
take enforcement action for any unpermitted discharges that occur between the
commencement of land disturbance and discharge authorization.
5. Late registration statements. Registration
statements for existing facilities covered under subdivision A 2 a of this
section will be accepted after the expiration date of this permit, but
authorization to discharge will not be retroactive. The VESMP authority,
department, and EPA reserve the right to take enforcement action for any
unpermitted discharges that occur after existing permit coverage expires and
prior to coverage under this permit is approved.
B. Registration statement. The operator shall
submit a complete and accurate registration statement to the VESMP authority
that contains the following information:
1.
Name, contact, mailing address, telephone number, and email address if
available of the construction activity operator. No more than one operator may
receive coverage under each registration statement;
General permit coverage will be issued to this operator, and
the certification in subdivision 18 of this subsection shall be signed by the
appropriate person associated with this operator as described in Part III K of
9VAC25-880-70.
2. State Corporation Commission entity
identification number if the operator is required to obtain an entity
identification number;
3. Name and
physical location address of the construction activity, when available, to be
covered under this general permit, including city or county, and latitude and
longitude in decimal degrees (six digits - ten-thousandths place);
4. A legible site map showing the location of
the existing or proposed land-disturbing activities for which the operator is
seeking permit coverage, the limits of land disturbance, construction
entrances, construction support activities, and all water bodies receiving
stormwater discharges from the construction site;
5. If off-site construction support
activities will be used, the name and physical location address, when
available, of all off-site construction support activities, including city or
county; latitude and longitude in decimal degrees (six digits - ten-thousandths
place); and whether or not the off-site construction support activity will be
covered under this general permit or a separate VPDES permit;
6. If excavated material (i.e., fill) will be
transported off the construction site for disposal, the name and physical
location address, when available, of all off-site excavated material disposal
areas, including city or county; latitude and longitude in decimal degrees (six
digits - ten-thousandths place); and the contents of the excavated
material;
7. Status of the
construction activity (i.e., federal, state, public, or private);
8. Nature of the construction activity (e.g.,
commercial, industrial, residential, agricultural, oil and gas);
9. If stormwater management or erosion and
sediment control plans for the construction activity have been approved by an
entity with department approved standards and specifications, a complete and
accurate standard and specification entity form shall be submitted with the
registration statement;
10. The
date of erosion and sediment control plan approval for the estimated area to be
disturbed during this permit term for construction activities that were
authorized to discharge under the expiring or expired 2019 general
permit;
11. If land disturbance has
commenced for construction activities that were authorized to discharge under
the expiring or expired 2019 general permit;
12. Name of the receiving waters and sixth
order Hydrologic Unit Code (HUC);
13. The name of the municipal separate storm
sewer system (MS4) operator if the construction activity discharges to an
MS4;
14. Estimated construction
activity start date and completion date;
15. Total area of the construction site and
estimated area to be disturbed by the construction activity during the 2024
general permit term (to the nearest one-hundredth of an acre);
16. If the area to be disturbed by the
construction activity is part of a larger common plan of development or
sale;
17. If nutrient credits will
be used to comply with the water quality design criteria requirements
(9VAC25-875-580), a letter of
availability from an appropriate nutrient bank that nonpoint source nutrient
credits are available; and
18. The
following certification: "I certify under penalty of law that I have read and
understand this registration statement and that this document and all
attachments were prepared in accordance with a system designed to assure that
qualified personnel properly gathered and evaluated the information submitted.
Based on my inquiry of the person or persons who manage the system or those
persons directly responsible for gathering the information, the information
submitted is to the best of my knowledge and belief true, accurate, and
complete. I am aware that there are significant penalties for submitting false
information including the possibility of fine and imprisonment for knowing
violations."
C. A
stormwater pollution prevention plan (SWPPP) shall be prepared in accordance
with this general permit prior to submitting the registration statement. By
signing the registration statement, the operator certifies that the SWPPP has
been prepared.
D. The registration
statement shall be signed in accordance with Part III K of
9VAC25-880-70.
Statutory Authority: §
62.1-44.15:25 of the Code of
Virginia.