Virginia Administrative Code
Title 9 - ENVIRONMENT
Agency 25 - STATE WATER CONTROL BOARD
Chapter 875 - VIRGINIA EROSION AND STORMWATER MANAGEMENT REGULATION
Part V - Criteria and Requirements for Regulated Land-Disturbing Activities
Article 1 - Administrative Criteria
Section 9VAC25-875-500 - Stormwater pollution prevention plan requirements
Current through Register Vol. 41, No. 3, September 23, 2024
A. A stormwater pollution prevention plan shall include an approved erosion and sediment control plan, an approved stormwater management plan, a pollution prevention plan for regulated land-disturbing activities, and a description of any additional control measures necessary to address a TMDL pursuant to subsection E of this section.
B. An erosion and sediment control plan consistent with the requirements of 9VAC25-875-550 must be designed and implemented during construction activities. Prior to land disturbance, this plan must be approved by the VESCP authority, VESMP authority, or the department.
C. A stormwater management plan consistent with the requirements of 9VAC25-875-510 must be designed and implemented during construction activities. Prior to land disturbance, this plan must be approved by the VESMP authority or the department.
D. A pollution prevention plan that identifies potential sources of pollutants that may reasonably be expected to affect the quality of stormwater discharges from the construction site and describe control measures that will be used to minimize pollutants in stormwater discharges from the construction site must be developed before land disturbance commences.
E. In addition to the requirements of subsections A through D of this section, if a specific wasteload allocation for a pollutant has been established in an approved TMDL and is assigned to stormwater discharges from a construction activity, additional control measures must be identified and implemented by the operator so that discharges are consistent with the assumptions and requirements of the wasteload allocation.
F. The stormwater pollution prevention plan (SWPPP) must address the following requirements as specified in 40 CFR 450.21, to the extent otherwise required by state law or regulations and any applicable requirements of a permit:
G. The SWPPP shall be amended whenever there is a change in design, construction, operation, or maintenance that has a significant effect on the discharge of pollutants to state waters and that has not been previously addressed in the SWPPP. The SWPPP must be maintained at a central location onsite. If an onsite location is unavailable, notice of the SWPPP's location must be posted near the main entrance at the construction site.
Statutory Authority: § 62.1-44.15:28 of the Code of Virginia; Chapters 68 and 758 of the 2016 Acts of Assembly.