Section 9VAC25-790-180 - CTC
Current through Register Vol. 41, No. 3, September 23, 2024
A. Issuance. Upon approval of the proposed design by the area engineer, including any submitted plans and specifications, if required, the director will issue a CTC to the owner within 15 days of such approval to construct or modify his sewerage systems or treatment works in accordance with the approved design and submitted plans and specifications.
B. Revisions. Any deviations from the approved design or the submitted plans and specifications significantly (25% or more variation from original for sewerage systems or treatment works and 20% or more for biosolids use facilities) affecting hydraulic conditions (flow profile), unit operations capacity, the functioning of the sewage treatment process, or the quality of treated effluent discharged, must be approved by the area engineer before any such changes are made. Revised plans and specifications shall be submitted in time to allow 30 days for the review, evaluation and approval of such plans or specifications before any construction work that will be affected by such changes is begun, unless the owner has received approval to proceed from the department prior to either a formal submittal of revisions, or the department approval of submitted revisions.
C. Completion of construction. A statement shall be submitted by the owner assuring completion of construction and an inspection of the constructed system works will be scheduled in accordance with the provisions of this chapter.
Statutory Authority
§ 62.1-44.15 of the Code of Virginia.