Section 9VAC25-740-180 - Operational flow requirements
Current through Register Vol. 41, No. 3, September 23, 2024
A. When the monthly average flow into a reclamation system or SRS reaches 95% of the designated design flow authorized by the VPDES or VPA permit issued to that system for each month of any three-month period, the permittee shall within 30 days notify the department in writing and within 90 days submit a plan of action for ensuring continued compliance with the terms of the permit.
B. The plan of action described in subsection A of this section shall include the necessary steps and a prompt schedule of implementation for controlling any current problem, or any problem that could be reasonably anticipated, resulting from high flows entering the reclamation system or SRS.
C. Upon receipt of the permittee's plan of action described in subsection A of this section, the department shall notify the owner whether the plan is approved or disapproved. If the plan is disapproved, such notification shall state the reasons and specify the actions necessary to obtain approval of the plan.
D. Failure to timely submit an adequate plan of action in accordance with subsection A of this section shall be deemed a violation of the permit.
E. Nothing herein shall in any way impair the authority of the department to take enforcement action under § 62.1-44.15, 62.1-44.23, or 62.1-44.32 of the Code of Virginia.
Statutory Authority: § 62.1-44.15 of the Code of Virginia.