Current through Register Vol. 41, No. 3, September 23, 2024
VWP GENERAL PERMIT NO. WP1 FOR IMPACTS LESS THAN ONE-HALF
ACRE UNDER THE VIRGINIA WATER PROTECTION PERMIT AND THE VIRGINIA STATE WATER
CONTROL LAW
In compliance with § 401 of the Clean Water Act, as
amended (33 USC §
1341) and the State Water Control Law and
regulations adopted pursuant thereto, the board has determined that there is a
reasonable assurance that this VWP general permit, if complied with, will
protect instream beneficial uses, will not violate applicable water quality
standards, and will not cause or contribute to a significant impairment of
state waters or fish and wildlife resources. In issuing this VWP general
permit, the board has not taken into consideration the structural stability of
any proposed activities.
The permanent or temporary impact of less than one-half acre
of nontidal wetlands or open water and up to 300 linear feet of nontidal stream
bed shall be subject to the provisions of the VWP general permit set forth
herein; any requirements in coverage granted under this VWP general permit; the
Clean Water Act, as amended; and the State Water Control Law and regulations
adopted pursuant to it.
Part I.
Special Conditions.
A. Authorized activities.
1. The activities authorized by this chapter
shall not cause more than the permanent or temporary impacts to less than
one-half acre of nontidal wetlands or open water and up to 300 linear feet of
nontidal stream bed. Additional permit requirements as stipulated by the
department in the coverage letter, if any, shall be enforceable conditions of
this permit.
2. Any changes to the
authorized permanent impacts to surface waters shall require a notice of
planned change in accordance with
9VAC25-660-80. An application or
request for modification to coverage or another VWP permit application may be
required.
3. Any changes to the
authorized temporary impacts to surface waters shall require written
notification to and approval from the Department of Environmental Quality in
accordance with
9VAC25-660-80 prior to initiating
the impacts and restoration to preexisting conditions in accordance with the
conditions of this permit.
4.
Modification to compensation requirements may be approved at the request of the
permittee when a decrease in the amount of authorized surface waters impacts
occurs, provided that the adjusted compensation meets the initial compensation
goals.
B. Overall
conditions.
1. The activities authorized by
this VWP general permit shall be executed in a manner so as to minimize adverse
impacts on instream beneficial uses as defined in §
62.1-10 (b) of
the Code of Virginia.
2. No
activity may substantially disrupt the movement of aquatic life indigenous to
the water body, including those species that normally migrate through the area,
unless the primary purpose of the activity is to impound water. Pipes and
culverts placed in streams must be installed to maintain low flow conditions
and shall be countersunk at both inlet and outlet ends of the pipe or culvert,
unless otherwise specifically approved by the Department of Environmental
Quality on a case-by-case basis, and as follows: The requirement to countersink
does not apply to extensions or maintenance of existing pipes and culverts that
are not countersunk, floodplain pipes and culverts being placed above ordinary
high water, pipes and culverts being placed on bedrock, or pipes and culverts
required to be placed on slopes 5.0% or greater. Bedrock encountered during
construction must be identified and approved in advance of a design change
where the countersunk condition cannot be met. Pipes and culverts 24 inches or
less in diameter shall be countersunk three inches below the natural stream bed
elevations, and pipes and culverts greater than 24 inches shall be countersunk
at least six inches below the natural stream bed elevations. Hydraulic capacity
shall be determined based on the reduced capacity due to the countersunk
position. In all stream crossings appropriate measures shall be implemented to
minimize any disruption of aquatic life movement.
3. Wet or uncured concrete shall be
prohibited from entry into flowing surface waters, unless the area is contained
within a cofferdam and the work is performed in the dry or unless otherwise
approved by the Department of Environmental Quality. Excess or waste concrete
shall not be disposed of in flowing surface waters or washed into flowing
surface waters.
4. All fill
material shall be clean and free of contaminants in toxic concentrations or
amounts in accordance with all applicable laws and regulations.
5. Erosion and sedimentation controls shall
be designed in accordance with the Virginia Erosion and Sediment Control
Handbook, Third Edition, 1992. These controls shall be placed prior to clearing
and grading and maintained in good working order to minimize impacts to state
waters. These controls shall remain in place until the area is stabilized and
shall then be removed.
6. Exposed
slopes and streambanks shall be stabilized immediately upon completion of work
in each permitted impact area. All denuded areas shall be properly stabilized
in accordance with the Virginia Erosion and Sediment Control Handbook, Third
Edition, 1992.
7. All construction,
construction access (e.g., cofferdams, sheetpiling, and causeways) and
demolition activities associated with the project shall be accomplished in a
manner that minimizes construction or waste materials from entering surface
waters to the maximum extent practicable, unless authorized by this VWP general
permit.
8. No machinery may enter
flowing waters, unless authorized by this VWP general permit or approved prior
to entry by the Department of Environmental Quality.
9. Heavy equipment in temporarily impacted
wetland areas shall be placed on mats, geotextile fabric, or other suitable
material to minimize soil disturbance to the maximum extent practicable.
Equipment and materials shall be removed immediately upon completion of
work.
10. All nonimpacted surface
waters and compensatory mitigation areas within 50 feet of authorized
activities and within the project or right-of-way limits shall be clearly
flagged or marked for the life of the construction activity at that location to
preclude unauthorized disturbances to these surface waters and compensatory
mitigation areas during construction. The permittee shall notify contractors
that no activities are to occur in these marked surface waters.
11. Temporary disturbances to surface waters
during construction shall be avoided and minimized to the maximum extent
practicable. All temporarily disturbed wetland areas shall be restored to
preexisting conditions within 30 days of completing work at each respective
temporary impact area, which shall include reestablishing preconstruction
elevations and contours with topsoil from the impact area where practicable and
planting or seeding with appropriate wetland vegetation according to cover type
(i.e., emergent, scrub-shrub, or forested). The permittee shall take all
appropriate measures to promote and maintain revegetation of temporarily
disturbed wetland areas with wetland vegetation through the second year
post-disturbance. All temporarily impacted streams and streambanks shall be
restored to their preconstruction elevations and contours with topsoil from the
impact area where practicable within 30 days following the construction at that
stream segment. Streambanks shall be seeded or planted with the same vegetation
cover type originally present, including any necessary, supplemental erosion
control grasses. Invasive species identified on the Department of Conservation
and Recreation's Virginia Invasive Plant Species List shall not be used to the
maximum extent practicable or without prior approval from the Department of
Environmental Quality.
12.
Materials (including fill, construction debris, and excavated and woody
materials) temporarily stockpiled in wetlands shall be placed on mats or
geotextile fabric, immediately stabilized to prevent entry into state waters,
managed such that leachate does not enter state waters, and completely removed
within 30 days following completion of that construction activity. Disturbed
areas shall be returned to preconstruction elevations and contours with topsoil
from the impact area where practicable; restored within 30 days following
removal of the stockpile; and restored with the same vegetation cover type
originally present, including any necessary, supplemental erosion control
grasses. Invasive species identified on the Department of Conservation and
Recreation's Virginia Invasive Plant Species List shall not be used to the
maximum extent practicable or without prior approval from the Department of
Environmental Quality.
13.
Continuous flow of perennial springs shall be maintained by the installation of
spring boxes, french drains, or other similar structures.
14. The permittee shall employ measures to
prevent spills of fuels or lubricants into state waters.
15. The permittee shall conduct his
activities in accordance with the time-of-year restrictions recommended by the
Virginia Department of Wildlife Resources, the Virginia Marine Resources
Commission, or other interested and affected agencies, as contained, when
applicable, in a Department of Environmental Quality VWP general permit
coverage letter, and shall ensure that all contractors are aware of the
time-of-year restrictions imposed.
16. Water quality standards shall not be
violated as a result of the construction activities.
17. If stream channelization or relocation is
required, all work in surface waters shall be done in the dry, unless otherwise
authorized by the Department of Environmental Quality, and all flows shall be
diverted around the channelization or relocation area until the new channel is
stabilized. This work shall be accomplished by leaving a plug at the inlet and
outlet ends of the new channel during excavation. Once the new channel has been
stabilized, flow shall be routed into the new channel by first removing the
downstream plug and then the upstream plug. The rerouted stream flow must be
fully established before construction activities in the old stream channel can
begin.
C. Road crossings.
1. Access roads and associated bridges,
pipes, and culverts shall be constructed to minimize the adverse effects on
surface waters to the maximum extent practicable. Access roads constructed
above preconstruction elevations and contours in surface waters must be
bridged, piped, or culverted to maintain surface flows.
2. Installation of road crossings shall occur
in the dry via the implementation of cofferdams, sheetpiling, stream
diversions, or other similar structures.
D. Utility lines.
1. All utility line work in surface waters
shall be performed in a manner that minimizes disturbance, and the area must be
returned to its preconstruction elevations and contours with topsoil from the
impact area where practicable and restored within 30 days of completing work in
the area, unless otherwise authorized by the Department of Environmental
Quality. Restoration shall be the seeding or planting of the same vegetation
cover type originally present, including any necessary, supplemental erosion
control grasses. Invasive species identified on the Department of Conservation
and Recreation's Virginia Invasive Plant Species List shall not be used to the
maximum extent practicable or without prior approval from the Department of
Environmental Quality.
2. Material
resulting from trench excavation may be temporarily sidecast into wetlands not
to exceed a total of 90 days, provided the material is not placed in a manner
such that it is dispersed by currents or other forces.
3. The trench for a utility line cannot be
constructed in a manner that drains wetlands (e.g., backfilling with extensive
gravel layers creating a french drain effect). For example, utility lines may
be backfilled with clay blocks to ensure that the trench does not drain surface
waters through which the utility line is installed.
E. Stream modification and stream bank
protection.
1. Riprap bank stabilization shall
be of an appropriate size and design in accordance with the Virginia Erosion
and Sediment Control Handbook, Third Edition, 1992.
2. Riprap apron for all outfalls shall be
designed in accordance with the Virginia Erosion and Sediment Control Handbook,
Third Edition, 1992.
3. For stream
bank protection activities, the structure and backfill shall be placed as close
to the stream bank as practicable. No material shall be placed in excess of the
minimum necessary for erosion protection.
4. All stream bank protection control
structures shall be located to eliminate or minimize impacts to vegetated
wetlands to the maximum extent practicable.
5. Asphalt and materials containing asphalt
or other toxic substances shall not be used in the construction of submerged
sills or breakwaters.
6.
Redistribution of existing stream substrate for the purpose of erosion control
is prohibited.
7. No material
removed from the stream bottom shall be disposed of in surface waters, unless
otherwise authorized by this VWP general permit.
F. Stormwater management facilities.
1. Stormwater management facilities shall be
installed in accordance with best management practices and watershed protection
techniques (e.g., vegetated buffers, siting considerations to minimize adverse
effects to aquatic resources, bioengineering methods incorporated into the
facility design to benefit water quality and minimize adverse effects to
aquatic resources) that provide for long-term aquatic resources protection and
enhancement, to the maximum extent practicable.
2. Compensation for unavoidable impacts shall
not be allowed within maintenance areas of stormwater management
facilities.
3. Maintenance
activities within stormwater management facilities shall not require additional
permit coverage or compensation, provided that the maintenance activities do
not exceed the original contours of the facility, as approved and constructed,
and are accomplished in designated maintenance areas as indicated in the
facility maintenance or design plan or when unavailable, an alternative plan
approved by the Department of Environmental Quality.
Part II.
Construction and Compensation Requirements, Monitoring, and
Reporting.
A. Minimum compensation
requirements.
1. The permittee shall provide
any required compensation for impacts in accordance with the conditions in this
VWP general permit, the coverage letter, and the chapter promulgating the
general permit.
2. Compensation
options that may be considered under this VWP general permit include the
purchase of mitigation bank credits or the purchase of in-lieu fee program
credits with a primary service area that covers the impact site in accordance
with §
62.1-44.15:23 of the Code of
Virginia, 9VAC25-660-70, and the associated
provisions of
9VAC25-210-116.
3. The final compensation plan shall be
submitted to and approved by the department prior to a construction activity in
permitted impacts areas. The department shall review and provide written
comments on the final plan within 30 days of receipt or it shall be deemed
approved. The final plan as approved by the department shall be an enforceable
requirement of any coverage under this VWP general permit. Deviations from the
approved final plan shall be submitted and approved in advance by the
department.
B. Impact
site construction monitoring.
1. Construction
activities authorized by this permit that are within impact areas shall be
monitored and documented. The monitoring shall consist of:
a. Preconstruction photographs taken at each
impact area prior to initiation of activities within impact areas. Photographs
remain on the project site and shall depict the impact area and the nonimpacted
surface waters immediately adjacent to and downgradient of each impact area.
Each photograph shall be labeled to include the following information: permit
number, impact area number, date and time of the photograph, name of the person
taking the photograph, photograph orientation, and photograph subject
description.
b. Site inspections
shall be conducted by the permittee or the permittee's qualified designee once
every calendar month during activities within impact areas. Monthly inspections
shall be conducted in the following areas: all authorized permanent and
temporary impact areas; all avoided surface waters, including wetlands, stream
channels, and open water; surface water areas within 50 feet of any land
disturbing activity and within the project or right-of-way limits; and all
on-site permanent preservation areas required under this permit. Observations
shall be recorded on the inspection form provided by the Department of
Environmental Quality. The form shall be completed in its entirety for each
monthly inspection and shall be kept on site and made available for review by
the Department of Environmental Quality staff upon request during normal
business hours. Inspections are not required during periods of no activity
within impact areas.
2.
Monitoring of water quality parameters shall be conducted during permanent
relocation of perennial streams through new channels in the manner noted in
this subdivision. The permittee shall report violations of water quality
standards to the Department of Environmental Quality in accordance with the
procedures in
9VAC25-660-100 Part II C.
Corrective measures and additional monitoring may be required if water quality
standards are not met. Reporting shall not be required if water quality
standards are not violated.
a. A sampling
station shall be located upstream and immediately downstream of the relocated
channel.
b. Temperature, pH, and
dissolved oxygen (D.O.) measurements shall be taken every 30 minutes for at
least two hours at each station prior to opening the new channels and
immediately before opening new channels.
c. Temperature, pH, and D.O. readings shall
be taken after opening the channels and every 30 minutes for at least three
hours at each station.
C. Reporting.
1. Written communications required by this
VWP general permit shall be submitted to the appropriate Department of
Environmental Quality office. The VWP general permit tracking number shall be
included on all correspondence.
2.
The Department of Environmental Quality shall be notified in writing prior to
the start of construction activities at the first authorized impact
area.
3. A construction status
update form provided by the Department of Environmental Quality shall be
completed and submitted to the Department of Environmental Quality twice per
year for the duration of coverage under a VWP general permit. Forms completed
in June shall be submitted by or on July 10, and forms completed in December
shall be submitted by or on January 10. The form shall include reference to the
VWP permit tracking number and one of the following statements for each
authorized surface water impact location:
a.
Construction activities have not yet started;
b. Construction activities have
started;
c. Construction activities
have started but are currently inactive; or
d. Construction activities are
complete.
4. The
Department of Environmental Quality shall be notified in writing within 30 days
following the completion of all activities in all authorized impact
areas.
5. The permittee shall
notify the Department of Environmental Quality in writing when unusual or
potentially complex conditions are encountered that require debris removal or
involve a potentially toxic substance. Measures to remove the obstruction,
material, or toxic substance or to change the location of a structure are
prohibited until approved by the Department of Environmental Quality.
6. The permittee shall report fish kills or
spills of oil or fuel immediately upon discovery. If spills or fish kills occur
between the hours of 8:15 a.m. to 5 p.m., Monday through Friday, the
appropriate Department of Environmental Quality regional office shall be
notified; otherwise, the Department of Emergency Management shall be notified
at 1-800-468-8892.
7. Violations of
state water quality standards shall be reported to the appropriate Department
of Environmental Quality office no later than the end of the business day
following discovery.
8. The
permittee shall notify the Department of Environmental Quality no later than
the end of the third business day following the discovery of additional impacts
to surface waters, including wetlands, stream channels, and open water that are
not authorized by the Department of Environmental Quality or to any required
preservation areas. The notification shall include photographs, estimated
acreage or linear footage of impacts, and a description of the
impacts.
9. Submittals required by
this VWP general permit shall contain the following signed certification
statement:
"I certify under penalty of law that this document and all
attachments were prepared under my direction or supervision in accordance with
a system designed to assure that qualified personnel properly gather and
evaluate the information submitted. Based on my inquiry of the person or
persons who manage the system, or those persons directly responsible for
gathering the information, the information submitted is, to the best of my
knowledge and belief, true, accurate, and complete. I am aware that there are
significant penalties for submitting false information, including the
possibility of fine and imprisonment for knowing violation."
Part III.
Conditions Applicable to All VWP General Permits.
A. Duty to comply. The permittee shall comply
with all conditions, limitations, and other requirements of the VWP general
permit; any requirements in coverage granted under this VWP general permit; the
Clean Water Act, as amended; and the State Water Control Law and regulations
adopted pursuant to it. Any VWP general permit violation or noncompliance is a
violation of the Clean Water Act and State Water Control Law and is grounds for
(i) enforcement action, (ii) VWP general permit coverage termination for cause,
(iii) VWP general permit coverage revocation, (iv) denial of application for
coverage, or (v) denial of an application for a modification to VWP general
permit coverage. Nothing in this VWP general permit shall be construed to
relieve the permittee of the duty to comply with all applicable federal and
state statutes, regulations, and toxic standards and prohibitions.
B. Duty to mitigate. The permittee shall take
all reasonable steps to minimize or prevent impacts in violation of the VWP
general permit that may have a reasonable likelihood of adversely affecting
human health or the environment.
C.
Reopener. This VWP general permit may be reopened to modify its conditions when
the circumstances on which the previous VWP general permit was based have
materially and substantially changed, or special studies conducted by the
department or the permittee show material and substantial change since the time
the VWP general permit was issued and thereby constitute cause for revoking and
reissuing the VWP general permit.
D. Compliance with state and federal law.
Compliance with this VWP general permit constitutes compliance with the VWP
permit requirements of the State Water Control Law. Nothing in this VWP general
permit shall be construed to preclude the institution of any legal action under
or relieve the permittee from any responsibilities, liabilities, or other
penalties established pursuant to any other state law or regulation or under
the authority preserved by § 510 of the Clean Water Act.
E. Property rights. Coverage under this VWP
general permit does not convey property rights in either real or personal
property or any exclusive privileges, nor does it authorize injury to private
property, any invasion of personal property rights, or any infringement of
federal, state, or local laws or regulations.
F. Severability. The provisions of this VWP
general permit are severable.
G.
Inspection and entry. Upon presentation of credentials, the permittee shall
allow the department or any duly authorized agent of the department, at
reasonable times and under reasonable circumstances, to enter upon the
permittee's property, public or private, and have access to inspect and copy
any records that must be kept as part of the VWP general permit conditions; to
inspect any facilities, operations, or practices (including monitoring and
control equipment) regulated or required under the VWP general permit; and to
sample or monitor any substance, parameter, or activity for the purpose of
ensuring compliance with the conditions of the VWP general permit or as
otherwise authorized by law. For the purpose of this section, the time for
inspection shall be deemed reasonable during regular business hours. Nothing
contained herein shall make an inspection time unreasonable during an
emergency.
H. Transferability of
VWP general permit coverage. VWP general permit coverage may be transferred to
another permittee when all of the criteria listed in this subsection are met.
On the date of the VWP general permit coverage transfer, the transferred VWP
general permit coverage shall be as fully effective as if it had been granted
directly to the new permittee.
1. The current
permittee notifies the department of the proposed transfer of the general
permit coverage and provides a written agreement between the current and new
permittees containing a specific date of transfer of VWP general permit
responsibility, coverage, and liability to the new permittee, or that the
current permittee will retain such responsibility, coverage, or liability,
including liability for compliance with the requirements of enforcement
activities related to the authorized activity.
2. The department does not within 15 days
notify the current and new permittees of the board's intent to modify or revoke
and reissue the VWP general permit.
I. Notice of planned change. VWP general
permit coverage may be modified subsequent to issuance in accordance with
9VAC25-660-80.
J. VWP general permit coverage termination
for cause. VWP general permit coverage is subject to termination for cause by
the department after public notice and opportunity for a hearing in accordance
with 9VAC25-210-180. Reasons for
termination for cause are as follows:
1.
Noncompliance by the permittee with any provision of this chapter, any
condition of the VWP general permit, or any requirement in general permit
coverage;
2. The permittee's
failure in the application or during the process of granting VWP general permit
coverage to disclose fully all relevant facts or the permittee's
misrepresentation of any relevant facts at any time;
3. The permittee's violation of a special or
judicial order;
4. A determination
by the department that the authorized activity endangers human health or the
environment and can be regulated to acceptable levels by a modification to the
VWP general permit coverage or a termination;
5. A change in any condition that requires
either a temporary or permanent reduction or elimination of any activity
controlled by the VWP general permit; or
6. A determination that the authorized
activity has ceased and that the compensation for unavoidable adverse impacts
has been successfully completed.
K. The department may terminate VWP general
permit coverage without cause when the permittee is no longer a legal entity
due to death or dissolution or when a company is no longer authorized to
conduct business in the Commonwealth. The termination shall be effective 30
days after notice of the proposed termination is sent to the last known address
of the permittee or registered agent, unless the permittee objects within that
time. If the permittee does object during that period, the department shall
follow the applicable procedures for termination under
9VAC25-210-180 and §
62.1-44.15:25 of the Code of
Virginia.
L. VWP general permit
coverage termination by consent. The permittee shall submit a request for
termination by consent within 30 days of completing or canceling all authorized
activities requiring notification under
9VAC25-660-50 A and all
compensatory mitigation requirements. When submitted for project completion,
the request for termination by consent shall constitute a notice of project
completion in accordance with
9VAC25-210-130 F. The director may
accept this termination of coverage on behalf of the department. The permittee
shall submit the following information:
1.
Name, mailing address, and telephone number;
2. Name and location of the
activity;
3. The VWP general permit
tracking number; and
4. One of the
following certifications:
a. For project
completion:
"I certify under penalty of law that all activities and any
required compensatory mitigation authorized by the VWP general permit and
general permit coverage have been completed. I understand that by submitting
this notice of termination I am no longer authorized to perform activities in
surface waters in accordance with the VWP general permit and general permit
coverage, and that performing activities in surface waters is unlawful where
the activity is not authorized by the VWP permit or coverage, unless otherwise
excluded from obtaining coverage. I also understand that the submittal of this
notice does not release me from liability for any violations of the VWP general
permit or coverage."
b. For
project cancellation:
"I certify under penalty of law that the activities and any
required compensatory mitigation authorized by the VWP general permit and
general permit coverage will not occur. I understand that by submitting this
notice of termination I am no longer authorized to perform activities in
surface waters in accordance with the VWP general permit and general permit
coverage, and that performing activities in surface waters is unlawful where
the activity is not authorized by the VWP permit or coverage, unless otherwise
excluded from obtaining coverage. I also understand that the submittal of this
notice does not release me from liability for any violations of the VWP general
permit or coverage, nor does it allow me to resume the authorized activities
without reapplication and coverage."
c. For events beyond permittee control, the
permittee shall provide a detailed explanation of the events, to be approved by
the Department of Environmental Quality, and the following certification
statement:
"I certify under penalty of law that the activities or the
required compensatory mitigation authorized by the VWP general permit and
general permit coverage have changed as the result of events beyond my control
(see attached). I understand that by submitting this notice of termination I am
no longer authorized to perform activities in surface waters in accordance with
the VWP general permit and general permit coverage, and that performing
activities in surface waters is unlawful where the activity is not authorized
by the VWP permit or coverage, unless otherwise excluded from obtaining
coverage. I also understand that the submittal of this notice does not release
me from liability for any violations of the VWP general permit or coverage, nor
does it allow me to resume the authorized activities without reapplication and
coverage."
M. Civil and criminal liability. Nothing in
this VWP general permit shall be construed to relieve the permittee from civil
and criminal penalties for noncompliance.
N. Oil and hazardous substance liability.
Nothing in this VWP general permit shall be construed to preclude the
institution of legal action or relieve the permittee from any responsibilities,
liabilities, or penalties to which the permittee is or may be subject under
§ 311 of the Clean Water Act or §§
62.1-44.34:14 through
62.1-44.34:23 of the State Water
Control Law.
O. Duty to cease or
confine activity. It shall not be a defense for a permittee in an enforcement
action that it would have been necessary to halt or reduce the activity for
which VWP general permit coverage has been granted in order to maintain
compliance with the conditions of the VWP general permit or coverage.
P. Duty to provide information.
1. The permittee shall furnish to the
department information that the department may request to determine whether
cause exists for modifying, revoking, or terminating VWP permit coverage or to
determine compliance with the VWP general permit or general permit coverage.
The permittee shall also furnish to the department, upon request, copies of
records required to be kept by the permittee.
2. Plans, maps, conceptual reports, and other
relevant information shall be submitted as required by the department prior to
commencing construction.
Q. Monitoring and records requirements.
1. Monitoring of parameters, other than
pollutants, shall be conducted according to approved analytical methods as
specified in the VWP general permit. Analysis of pollutants will be conducted
according to 40 CFR Part 136 as published in the July 1, 2023, update,
Guidelines Establishing Test Procedures for the Analysis of
Pollutants.
2. Samples and
measurements taken for the purpose of monitoring shall be representative of the
monitored activity.
3. The
permittee shall retain records of all monitoring information, including all
calibration and maintenance records and all original strip chart or electronic
recordings for continuous monitoring instrumentation, copies of all reports
required by the VWP general permit, and records of all data used to complete
the application for coverage under the VWP general permit, for a period of at
least three years from the date of general permit expiration. This period may
be extended by request of the department at any time.
4. Records of monitoring information shall
include, as appropriate:
a. The date, exact
place, and time of sampling or measurements;
b. The name of the individuals who performed
the sampling or measurements;
c.
The date and time the analyses were performed;
d. The name of the individuals who performed
the analyses;
e. The analytical
techniques or methods supporting the information such as observations,
readings, calculations, and bench data used;
f. The results of such analyses;
and
g. Chain of custody
documentation.
R. Unauthorized discharge of pollutants.
Except in compliance with this VWP general permit, it shall be unlawful for the
permittee to:
1. Discharge into state waters
sewage, industrial wastes, other wastes, or any noxious or deleterious
substances;
2. Excavate in a
wetland;
3. Otherwise alter the
physical, chemical, or biological properties of state waters and make them
detrimental to the public health, to animal or aquatic life, or to the uses of
such waters for domestic or industrial consumption, for recreation, or for
other uses; or
4. On and after
October 1, 2001, conduct the following activities in a wetland:
a. New activities to cause draining that
significantly alter or degrade existing wetland acreage or functions;
b. Filling or dumping;
c. Permanent flooding or impounding;
or
d. New activities that cause
significant alteration or degradation of existing wetland acreage or
functions.
S.
Duty to reapply. Any permittee desiring to continue a previously authorized
activity after the expiration date of the VWP general permit shall comply with
the provisions in
9VAC25-660-27.
Statutory Authority: §
62.1-44.15 of the Code of
Virginia; § 401 of the Clean Water Act (33 USC §
1251 et
seq.)