Virginia Administrative Code
Title 9 - ENVIRONMENT
Agency 25 - STATE WATER CONTROL BOARD
Chapter 580 - UNDERGROUND STORAGE TANKS: TECHNICAL STANDARDS AND CORRECTIVE ACTION REQUIREMENTS
Part X - UST Systems with Field-Constructed Tanks and Airport Hydrant Fuel Distribution Systems
Section 9VAC25-580-390 - Additions, exceptions, and alternatives for UST systems with field-constructed tanks and airport hydrant systems
Current through Register Vol. 41, No. 3, September 23, 2024
A. Exception to piping secondary containment requirements. Owners and operators may use single walled piping when installing or replacing piping associated with UST systems with field-constructed tanks greater than 50,000 gallons and piping associated with airport hydrant systems. Piping associated with UST systems with field-constructed tanks less than or equal to 50,000 gallons not part of an airport hydrant system must meet the secondary containment requirement when installed or replaced.
B. Upgrade requirements. Not later than January 1, 2021, airport hydrant systems and UST systems with field-constructed tanks where installation commenced before January 1, 2018, must meet the following requirements or be permanently closed pursuant to Part VII (9VAC25-580-310 et seq.) of this chapter.
Note: The following codes of practice may be used to comply with subsection B of this section:
C. Walkthrough inspections. In addition to the walkthrough inspection requirements in 9VCA25-580-85, owners and operators must inspect the following additional areas for airport hydrant systems at least once every 30 days if confined space entry according to the Occupational Safety and Health Administration (see 29 CFR Part 1910) is not required or at least annually if confined space entry is required and keep documentation of the inspection according to 9VAC25-580-85 B.
D. Release detection. Owners and operators of UST systems with field-constructed tanks and airport hydrant systems must begin meeting the release detection requirements described in this part not later than January 1, 2021.
Maximum Leak Detection Rate Per Test Section Volume |
||
Test Section Volume (Gallons) |
Semiannual Test - Leak Detection Rate Not To Exceed (Gallons Per Hour) |
Annual Test - Leak Detection Rate Not To Exceed (Gallons Per Hour) |
< 50,000 |
1.0 |
0.5 |
>= 50,000 to < 75,000 |
1.5 |
0.75 |
>= 75,000 to < 100,000 |
2.0 |
1.0 |
>= 100,000 |
3.0 |
1.5 |
Phase in for Piping Segments >= 100,000 Gallons in Volume |
|
First test |
Not later than January 1, 2021, (may use up to 6.0 gph leak rate) |
Second test |
Between January 1, 2021, and January 1, 2024, (may use up to 6.0 gph leak rate) |
Third test |
Between January 1, 2024, and January 1, 2025, (must use 3.0 gph for leak rate) |
Subsequent tests |
After January 1, 2025, begin using semiannual or annual line testing according to the Maximum Leak Detection Rate Per Test Section Volume table above |
E. Applicability of closure requirements to previously closed UST systems. When directed by the department, the owner and operator of an UST system with field-constructed tanks or airport hydrant system permanently closed before January 1, 2018, must assess the excavation zone and close the UST system in accordance with Part VII of this chapter if releases from the UST may, in the judgment of the department, pose a current or potential threat to human health and the environment.
Statutory Authority: §§ 62.1-44.15 and 62.1-44.34:9 of the Code of Virginia; 42 USC § 6901 et seq.; 40 CFR Parts 280 and 281.