A. To properly operate and maintain UST systems, not later than January 1, 2021, owners and operators must meet one of the following:

1. Conduct a walkthrough inspection that, at a minimum, checks the following equipment as specified below:
a. Every 30 days (Exception: spill prevention equipment at UST systems receiving deliveries at intervals greater than every 30 days may be checked prior to each delivery):
(1) Spill prevention equipment - visually check for damage; remove liquid or debris; check for and remove obstructions in the fill pipe; check the fill cap to make sure it is securely on the fill pipe; and, for double walled spill prevention equipment with interstitial monitoring, check for a leak in the interstitial area; and

(2) Release detection equipment - check to make sure the release detection equipment is operating with no alarms or other unusual operating conditions present and ensure records of release detection testing are reviewed and current; and

b. Annually:
(1) Containment sumps - visually check for damage, leaks to the containment area, or releases to the environment; remove liquid (in contained sumps) or debris; and, for double walled sumps with interstitial monitoring, check for a leak in the interstitial area; and

(2) Handheld release detection equipment - check devices such as tank gauge sticks or groundwater bailers for operability and serviceability;

2. Conduct operation and maintenance walkthrough inspections according to a standard code of practice developed by a nationally recognized association or independent testing laboratory that checks equipment comparable to subdivision 1 of this subsection; or

3. Conduct operation and maintenance walkthrough inspections according to a protocol developed by the department that checks equipment comparable to subdivision 1 of this subsection.

B. Owners and operators must maintain records (in accordance with 9VAC25-580-120) of operation and maintenance walkthrough inspections for one year. Records must include a list of each area checked, whether each area checked was acceptable or needed action taken, a description of actions taken to correct an issue, and delivery records if spill prevention equipment is checked less frequently than every 30 days due to infrequent deliveries.

NOTE: The following code of practice may be used to comply with subdivision A 2 of this section: Petroleum Equipment Institute Recommended Practice RP 900, Recommended Practices for the Inspection and Maintenance of UST Systems.

Statutory Authority: §§ 62.1-44.15 and 62.1-44.34:9 of the Code of Virginia; 42 USC § 6901 et seq.; 40 CFR Parts 280 and 281.

Disclaimer: These regulations may not be the most recent version. Virginia may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.