Section 9VAC25-580-82 - Periodic testing of spill prevention equipment and containment sumps used for interstitial monitoring of piping and periodic inspection of overfill prevention equipment
Current through Register Vol. 41, No. 3, September 23, 2024
A. Owners and operators of UST systems with spill and overfill prevention equipment and containment sumps used for interstitial monitoring of piping must meet these requirements to ensure the equipment is operating properly and will prevent releases to the environment:
NOTE: The following code of practice may be used to comply with subdivisions A 1 b and A 2 of this section: Petroleum Equipment Institute Publication RP 1200, Recommended Practices for the Testing and Verification of Spill, Overfill, Leak Detection and Secondary Containment Equipment at UST Facilities.
B. Owners and operators must begin meeting these requirements as follows:
C. Owners and operators must maintain records as follows in accordance with 9VAC25-580-120 for spill prevention equipment, containment sumps used for interstitial monitoring of piping, and overfill prevention equipment:
Statutory Authority: §§ 62.1-44.15 and 62.1-44.34:9 of the Code of Virginia; 42 USC § 6901 et seq.; 40 CFR Parts 280 and 281.