The applicant shall demonstrate to the satisfaction of the department that the project meets an established need for water to meet the project purpose. In establishing need, the applicant shall provide the following information:
1. Existing supply sources, yields, and demands, including:
2. Projected demands over a minimum 30-year planning period, including the following:
3. Any alternatives analysis conducted specifically for withdrawals for public water supply shall include:
4. Any alternatives analysis conducted for surface water withdrawals other than for public water supply shall include the following items of subdivision 3 of this section: subdivisions 3a(3), 3a(4), and 3c. The analysis shall also include applicable items of subdivisions 3a(1), 3a(2), and 3b.
Statutory Authority: § 62.1-44.15 of the Code of Virginia; § 401 of the Clean Water Act (33 USC § 1251 et seq.).