Section 9VAC25-151-80 - Stormwater pollution prevention plans
Current through Register Vol. 41, No. 3, September 23, 2024
A stormwater pollution prevention plan (SWPPP) shall be developed and implemented for the facility covered by this permit. The SWPPP is intended to document the selection, design, and installation of control measures, including BMPs, to minimize the pollutants in all stormwater discharges from the facility, and to meet applicable effluent limitations and water quality standards.
The SWPPP requirements of this general permit may be fulfilled, in part, by incorporating by reference other plans or documents (i.e., a spill prevention control and countermeasure (SPCC) plan developed for the facility under § 311 of the Clean Water Act, or best management practices (BMP) programs otherwise required for the facility), provided that the incorporated plan meets or exceeds the plan requirements of Part III B. All plans incorporated by reference into the SWPPP become enforceable under this permit. If a plan incorporated by reference does not contain all of the required elements of the SWPPP of Part III B, the permittee shall develop the missing SWPPP elements and include them in the required plan.
A. Deadlines for SWPPP preparation and compliance.
B. Contents of the SWPPP. The contents of the SWPPP shall comply with the requirements listed below and those in the appropriate sectors of Part IV. These requirements are cumulative. If a facility has colocated industrial activities that are covered in more than one sector of Part IV, that facility's SWPPP shall comply with the requirements listed in all applicable sectors. The following requirements are applicable to all SWPPPs developed under this general permit. The SWPPP shall include, at a minimum, the following items:
Selection of control measures shall take into consideration:
Structural control measures may require a separate permit under § 404 of the Clean Water Act and the Virginia Water Protection Permit Program Regulation (9VAC25-210) before installation begins.
Any deficiencies in the implementation of the SWPPP that are found shall be corrected as soon as practicable, but not later than within 60 days of the inspection, unless permission for a later date is granted in writing by the director. The results of the inspections shall be documented in the SWPPP and shall include at a minimum:
C. Maintenance. The SWPPP shall include a description of procedures and a regular schedule for preventive maintenance of all control measures, and shall include a description of the back-up practices that are in place should a runoff event occur while a control measure is off-line. The effectiveness of nonstructural control measures shall also be maintained by appropriate means (e.g., spill response supplies available and staff trained, etc.).
All control measures identified in the SWPPP shall be maintained in effective operating condition and shall be observed at least annually when a stormwater discharge is occurring to ensure that they are functioning correctly. Where discharge locations are inaccessible, nearby downstream locations shall be observed. The observations shall be documented in the SWPPP.
If routine facility inspections required by Part III B 5 identify control measures that are not operating effectively, repairs or maintenance shall be performed before the next anticipated storm event. If maintenance before the next anticipated storm event is not possible, maintenance shall be scheduled and accomplished as soon as practicable, but not later than within 60 days of the inspection, unless permission for a later date is granted in writing by the director. In the interim, back-up measures shall be employed and documented in the SWPPP until repairs or maintenance is complete. Documentation shall be kept with the SWPPP of maintenance and repairs of control measures, including the dates of regular maintenance, dates of discovery of areas in need of repair or replacement, dates for repairs, dates that the control measures returned to full function, and the justification for any extended maintenance or repair schedules.
D. Nonstormwater discharges.
E. Signature and SWPPP review.
The director may notify the permittee at any time that the SWPPP, control measures, or other components of the facility's stormwater program do not meet one or more of the requirements of this permit. The notification shall identify specific provisions of the permit that are not being met, and may include required modifications to the stormwater program, additional monitoring requirements, and special reporting requirements. The permittee shall make any required changes to the SWPPP within 60 days of receipt of the notification, unless permission for a later date is granted in writing by the director, and shall submit a written certification to the director that the requested changes have been made.
F. Maintaining an updated SWPPP.
Statutory Authority: § 62.1-44.15 of the Code of Virginia; § 402 of the Clean Water Act; 40 CFR Parts 122, 123, and 124.