Section 9VAC20-81-810 - Permits for CCR landfills and CCR surface impoundments

Universal Citation: 9 VA Admin Code 20-81-810

Current through Register Vol. 41, No. 3, September 23, 2024

A. CCR landfills are a specific type of industrial landfill. Permit requirements for industrial landfills are outlined in Part III (9VAC20-81-100 et seq.) and Part V (9VAC20-81-400 et seq.) of this chapter and must be complied with in addition to the requirements applicable to CCR landfills found in this part. Existing CCR landfills shall submit a complete permit application no later than October 17, 2017. Owners and operators of new CCR landfills are required to submit to the director a permit application for an industrial landfill that meets the requirements of this chapter and receive a permit for an industrial landfill prior to the initial receipt of CCR in the CCR unit. An application for a CCR landfill or lateral expansion of a CCR landfill shall include the following:

1. Location restriction demonstrations required by 40 CFR 257.60, 40 CFR 257.61, 40 CFR 257.62, 40 CFR 257.63, and 40 CFR 257.64, as applicable;

2. Description of the CCR landfill's design criteria required by 40 CFR 257.70 (new CCR landfill or lateral expansion of a CCR landfill);

3. Description of how the CCR landfill's operating criteria required by 40 CFR 257.80, 40 CFR 257.81, and 40 CFR 257.84 are met;

4. Explanation of how groundwater monitoring and corrective action criteria required by 40 CFR 257.90, 40 CFR 257.91, 40 CFR 257.93, 40 CFR 257.94, 40 CFR 257.95, 40 CFR 257.96, 40 CFR 257.97, and 40 CFR 257.98 are met;

5. Explanation of how closure and post-closure care requirements found in 40 CFR 257.101, 40 CFR 257.102, 40 CFR 257.103, and 40 CFR 257.104 will be met;

6. Website address for information required to be posted by 40 CFR 257.105, 40 CFR 257.106, and 40 CFR 257.107; and

7. Part III requirements concerning industrial landfills. If more than one standard is listed, the more stringent standard is to be complied with unless the director has granted a variance to a more stringent state specific standard.

B. Existing CCR surface impoundments are required to submit to the director a permit application for a CCR surface impoundment permit that meets the requirements of this chapter before October 17, 2017. New CCR surface impoundments are required to submit to the director a permit application for a surface impoundment that meets the requirements of this chapter prior to the initial receipt of CCR in the CCR unit. An application for a CCR surface impoundment shall include the following:

1. Location restriction demonstrations required by 40 CFR 257.60, 40 CFR 257.61, 40 CFR 257.62, 40 CFR 257.63, and 40 FR 257.64;

2. Description of the CCR surface impoundment's design criteria required by 40 CFR 257.71 (existing CCR surface impoundments), 40 CFR 257.72 (new CCR surface impoundments and lateral expansions), 40 CFR 257.73 (existing CCR surface impoundments), and 40 CFR 257.74 (new CCR surface impoundments and lateral expansions) as applicable;

3. Description of how the CCR surface impoundment's operating criteria required by 40 CFR 257.80, 40 CFR 257.82, and 40 CFR 257.83 are met;

4. Explanation of how groundwater monitoring and corrective action criteria required by 40 CFR 257.90, 40 CFR 257.91, 40 CFR 257.93, 40 CFR 257.94, 40 CFR 257.95, 40 CFR 257.96, 40 CFR 257.97, and 40 CFR 257.98 are met;

5. Explanation of how closure and post-closure care requirements found in 40 CFR 257.101, 40 CFR 257.102, 40 CFR 257.103, and 40 CFR 257.104 will be met; and

6. Website address for information required to be posted by 40 CFR 257.105, 40 CFR 257.106, and 40 CFR 257.107.

C. CCR landfills and new and existing surface impoundments are required to comply with the applicable permitting provisions in Part V (9VAC20-81-400 et seq.) of this chapter, including Virginia public participation requirements.

D. Inactive CCR surface impoundments were not subject to (i) this chapter during their operating life or (ii) a solid waste permit for operation. Inactive CCR surface impoundments are subject to a solid waste permit to address closure and post-closure, as applicable, except where the applicable requirements are included in an existing solid waste permit or a permit issued under State Water Control Law. Such permit shall include conditions to comply with applicable requirements established pursuant to 9VAC20-81-820.

Statutory Authority: § 10.1-1402 of the Code of Virginia; 42 USC § 6941 et seq.; 40 CFR Parts 257 and 258.

Disclaimer: These regulations may not be the most recent version. Virginia may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.