Virginia Administrative Code
Title 9 - ENVIRONMENT
Agency 15 - DEPARTMENT OF ENVIRONMENTAL QUALITY
Chapter 40 - SMALL RENEWABLE ENERGY PROJECTS (WIND) PERMIT BY RULE
Part II - Permit by Rule Provisions
Section 9VAC15-40-100 - Change of ownership, project modifications, termination

Universal Citation: 9 VA Admin Code 15-40-100

Current through Register Vol. 41, No. 3, September 23, 2024

A. Change of ownership. A permit by rule may be transferred to a new owner or operator if:

1. The current owner or operator notifies the department at least 30 days in advance of the transfer date by submittal of a notice per subdivision 2 of this subsection;

2. The notice shall include a written agreement between the existing and new owner or operator containing a specific date for transfer of permit responsibility, coverage, and liability between them; and

3. The transfer of the permit by rule to the new owner or operator shall be effective on the date specified in the agreement described in subdivision 2 of this subsection.

B. Project modifications. Provided project modifications are in accordance with the requirements of this permit by rule and do not increase the rated capacity of the small wind energy project, the owner or operator of a project authorized under a permit by rule may modify its design or operation or both by furnishing to the department new certificates prepared by a professional engineer, new documentation required under 9VAC15-40-30, and the appropriate fee in accordance with 9VAC15-40-110. The department shall review the received modification submittal in accordance with the provisions of subsection B of 9VAC15-40-30.

C. Permit by rule termination. The department may terminate the permit by rule whenever the department finds that:

1. The applicant has knowingly or willfully misrepresented or failed to disclose a material fact in any report or certification required under this chapter; or

2. After the department has taken enforcement actions pursuant to 9VAC15-40-140, the owner or operator persistently operates the project in significant violation of the project's mitigation plan.

Prior to terminating a permit by rule pursuant to subdivision 1 or 2 of this subsection, the department shall hold an informal fact-finding proceeding pursuant to § 2.2-4019 of the Virginia Administrative Process Act in order to assess whether to continue with termination of the permit by rule or to issue any other appropriate order. If the department determines that it should continue with the termination of the permit by rule, the department shall hold a formal hearing pursuant to § 2.2-4020 of the Virginia Administrative Process Act. Notice of the formal hearing shall be delivered to the owner or operator. Any owner or operator whose permit by rule is terminated by the department shall cease operating his small wind energy project.

Statutory Authority

§ 10.1-1197.6 of the Code of Virginia.

Disclaimer: These regulations may not be the most recent version. Virginia may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.