A. This section shall apply whenever an applicant or permittee must complete an erosion and sediment control plan under 4VAC25-150-260. The erosion and sediment control plan shall also describe how stormwater runoff will be managed in accordance with the standards of this section.
B. Areas downstream from permitted sites shall be protected from sediment disposition, erosion and damage due to increases in volume, velocity and peak flow rates of stormwater runoff for the stated frequency storm of 24-hour duration in accordance with the following:
C. Stormwater runoff which has been contaminated by or come into contact with overburden, raw material, intermediate products, finished products, byproducts or wastes from gas, oil or geophysical operations located on the permitted site shall be managed in accordance with a plan approved by the director.
D. The director may waive or modify any of the requirements of this section that are deemed inappropriate or too restrictive for site conditions. The permittee's written request for a variance shall document the need for the variance and describe the alternate measures or practices to be used. Specific variances allowed by the director shall be documented in the operations plan. The director shall consider variance requests judiciously, keeping in mind both the need of the applicant to maximize cost effectiveness and the need to protect off-site properties and resources from damage.
Statutory Authority