Virginia Administrative Code
Title 4 - CONSERVATION AND NATURAL RESOURCES
Agency 25 - DEPARTMENT OF ENERGY
Chapter 130 - COAL SURFACE MINING RECLAMATION REGULATIONS
Part 825 - Special Permanent Program Performance Standards-Remining Areas with Pollutional Discharges
Section 4VAC25-130-825.11 - Operational requirements

Universal Citation: 4 VA Admin Code 25-130-825-11

Current through Register Vol. 41, No. 3, September 23, 2024

A permittee who receives an authorization to mine areas with preexisting pollutional discharges under 4VAC25-130-785.19 shall comply with the requirements of this Subchapter except as specifically modified by this Part. The permittee shall also:

(1) Implement the approved water quality and quantity monitoring program for the pollution abatement area until the requirements of 4VAC25-130-825.14 are met.

(2) Implement the approved abatement plan.

(3) Notify the division immediately prior to the completion of each step of the abatement plan.

(4) Provide progress reports to the division within 30 days after the completion of each step of the abatement program that all work has been performed in accordance with the terms and conditions of the pollution abatement authorization and the approved maps, plans, cross-sections, and specifications.

Statutory Authority

§§ 45.1-161.3 and 45.1-230 of the Code of Virginia.

Disclaimer: These regulations may not be the most recent version. Virginia may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.