Virginia Administrative Code
Title 4 - CONSERVATION AND NATURAL RESOURCES
Agency 25 - DEPARTMENT OF ENERGY
Chapter 130 - COAL SURFACE MINING RECLAMATION REGULATIONS
Part 816 - Permanent Program Performance Standards-Surface Mining Activities
Section 4VAC25-130-816.107 - Backfilling and grading; steep slopes
Current through Register Vol. 41, No. 3, September 23, 2024
(a) Surface mining activities on steep slopes shall be conducted so as to meet the requirements of 4VAC25-130-816.102 through 4VAC25-130-816.106, and the requirements of this section except where mining is conducted on flatter gently rolling terrain with an occasional steep slope through which the mining proceeds and leaves a plain or predominantly flat area or where operations are conducted in accordance with Part 824.
(b) The following materials shall not be placed or allowed to remain on the downslope:
(c) Land above the highwall shall not be disturbed unless the division finds that this disturbance will facilitate compliance with the environmental protection standards of this Subchapter and the disturbance is limited to that necessary to facilitate compliance.
(d) Woody materials shall not be buried in the backfilled area unless the division determines that the proposed method for placing woody material within the backfill will not deteriorate the stable condition of the backfilled area.
(e) The permittee must demonstrate to the division, using standard geotechnical analysis, that the minimum static factor of safety for the stability of all portions of the reclaimed land is at least 1.3. A lower or higher factor of safety may be specified by the division upon a finding that the backfilled area will not present any actual or probable hazard to public property, health, safety, and the environment. The factor of safety specified shall be based on accepted geotechnical engineering analyses. A lower factor of safety shall be approved only upon a demonstration that:
(f) Drainage channels or roads which are approved under 4VAC25-130-816.133 for the postmining land use and which are to be located in the uppermost portion of the backfilled area shall be approved by the division only upon a finding that the highwall shall be completely covered. The division may approve incorporating the drainage channel or road as an integral part of the backfilled area with the requirements to blend or shave the highwall into the natural terrain, if the standards of this section are satisfied.
Statutory Authority
§§ 45.1-161.3 and 45.1-230 of the Code of Virginia.