Section 4VAC25-130-784.23 - Operation plan; maps and plans
Current through Register Vol. 41, No. 3, September 23, 2024
Each application shall contain maps and plans as follows:
(a) The maps, plans and cross sections shall show the land proposed to be affected throughout the operation, the underground mining activities to be conducted, and any change in a facility or feature to be caused by the proposed operations, if the facility or feature was shown under 4VAC25-130-783.24 and 4VAC25-130-783.25.
(b) The following shall be shown for the proposed permit area:
(c) Maps, plans, and cross sections required under paragraphs (b) (4), (5), (6), (10), and (11) of this section shall be prepared by, or under the direction of and certified by a qualified registered professional engineer, or certified professional geologist, with assistance from experts in related fields, such as land surveying and landscape architecture, except that-