Section 4VAC25-130-780.13 - Operation plan; blasting

Universal Citation: 4 VA Admin Code 25-130-780-13

Current through Register Vol. 41, No. 3, September 23, 2024

(a) Blasting plan. Each application shall contain a blasting plan for the proposed permit area, explaining how the applicant will comply with the requirements of 4VAC25-130-816.61 through 4VAC25-130-816.68. This plan shall include, at a minimum, information setting forth the limitations the permittee will meet with regard to ground vibration and airblast, the bases for those limitations, and the methods to be applied in controlling the adverse effects of blasting operations.

(b) Monitoring system. Each application shall contain a description of any system to be used to monitor compliance with the standards of 4VAC25-130-816.67 including the type, capability, and sensitivity of any blast-monitoring equipment and proposed procedures and locations of monitoring.

(c) Blasting near underground mines. Blasting operations within 500 feet of active underground mines require approval of the State and Federal regulatory authorities concerned with the health and safety of underground miners.

Statutory Authority

§§ 45.1-161.3 and 45.1-230 of the Code of Virginia.

Disclaimer: These regulations may not be the most recent version. Virginia may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.