Virginia Administrative Code
Title 4 - CONSERVATION AND NATURAL RESOURCES
Agency 25 - DEPARTMENT OF ENERGY
Chapter 130 - COAL SURFACE MINING RECLAMATION REGULATIONS
Part 773 - Requirements for Permits and Permit Processing
Section 4VAC25-130-773.19 - Permit issuance and right of renewal
Current through Register Vol. 41, No. 3, September 23, 2024
(a) Decision. If the application is approved, the permit shall be issued upon submittal of a performance bond in accordance with Subchapter VJ. If the application is disapproved, specific reasons therefore shall be set forth in the notification required by Paragraph (b) of this section.
(b) Notification. The division shall issue written notification of the decision to the following persons and entities:
(c) Permit term. Each permit shall be issued for a fixed term of 5 years or less, unless the requirements of 4VAC25-130-778.17 are met.
(d) Right of renewal. Permit application approval shall apply to those lands that are specifically designated as the permit area on the maps submitted with the application and for which the application is complete and accurate. Any valid permit issued in accordance with Paragraph (a) of this section shall carry with it the right of successive renewal, within the approved boundaries of the existing permit, upon expiration of the term of the permit, in accordance with 4VAC25-130-774.15.
(e) Initiation of operations.
Statutory Authority
§§ 45.1-161.3 and 45.1-230 of the Code of Virginia.