Utah Administrative Code
Topic - Public Service Commission
Title R746 - Administration
Rule R746-440 - Voluntary Resource Decision
Section R746-440-2 - Process for Approval of a Resource Decision
Universal Citation: UT Admin Code R 746-440-2
Current through Bulletin 2025-06, March 15, 2025
(1) Following a filing of a request for approval of a Resource decision:
(a) At a
scheduling conference, the Commission will set an intervention deadline and
schedule the time for conducting a public hearing on the request. The
Commission will issue a Scheduling Order subsequent to the scheduling
conference.
(b) The Commission will
issue a protective order, to facilitate access to and exchange of information
which is claimed to be confidential or of a proprietary nature.
(c) Discovery may commence. Responses to
discovery requests shall be made within 21 calendar days after receipt, or as
otherwise agreed between the parties or ordered by the Commission.
(d) Delivery of documents may be made by
electronic means (e.g., email, disk, facsimile), instead of paper versions, as
agreed by the parties or as ordered by the Commission.
(2) The Energy utility shall maintain a complete record of all materials submitted to the Commission and all materials submitted in response to discovery requests during a Resource decision process for 10 years from the date of the Commission's final order in a Resource decision proceeding. A party to a proceeding may petition the Commission to require specified additional materials to be maintained for a specified period.
Disclaimer: These regulations may not be the most recent version. Utah may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.