(1) General
Requirements of a Solicitation Process.
(a)
All aspects of a Solicitation and Solicitation Process must be fair, reasonable
and in the public interest.
(b) A
proposed Solicitation and Solicitation Process must be reasonably designed to:
(i) Comply with all applicable requirements
of the Act and Commission rules;
(ii) Be in the public interest taking into
consideration:
(A) whether they are
reasonably designed to lead to the acquisition, production, and delivery of
electricity at the lowest reasonable cost to the retail customers of the
Soliciting Utility located in this state;
(B) long-term and short-term
impacts;
(E) financial impacts on the Soliciting
Utility; and
(F) other factors
determined by the Commission to be relevant;
(iii) Be sufficiently flexible to permit the
evaluation and selection of those resources or combination of resources
determined by the Commission to be in the public interest;
(iv) Be designed to solicit a robust set of
bids to the extent practicable; and
(v) Be commenced sufficiently in advance of
the time of the projected resource need to permit and facilitate compliance
with the Act and the Commission rules and a reasonable evaluation of resource
options that can be available to fill the projected need and that will satisfy
the criteria contained within Section
54-17-302(3)(c).
The utility may request an expedited review of the proposed Solicitation and
Solicitation Process if changed circumstances or new information require a
different acquisition timeline. The Soliciting Utility must demonstrate to the
Commission that the timing of the Solicitation Process will nevertheless
satisfy the criteria established in the Act and in Commission rules.
(2) Screening Criteria
- Screening in A Solicitation Process.
(a) In
preparing a Solicitation and in evaluating bids, the Soliciting Utility shall
develop and utilize, in consultation with the Independent Evaluator (if then
under contract) and the Division of Public Utilities, screening and evaluation
criteria, ranking factors and evaluation methodologies that are reasonably
designed to ensure that the Solicitation Process is fair, reasonable and in the
public interest.
(b) Reasonable
initial screening criteria may include, but are not necessarily limited to,
reasonable and nondiscriminatory evaluation of and initial rankings based upon
the following factors:
(i) Cost to utility
ratepayers;
(ii) Timing of
deliveries;
(iv)
Dispatchability/flexibility;
(vi) Level of
change to pro forma contracts included in an approved Solicitation
Process;
(vii) Transmission,
Interconnection and Integration costs and benefits;
(viii) Commission-approved consideration of
impacts of direct or inferred debt;
(ix) Feasibility, including project timing
and the process for obtaining necessary rights and permits;
(x) Adequacy and flexibility of fuel
supplies;
(xi) Choice of cooling
technology and adequacy of water resources;
(xii) Systemwide benefits of transmission
infrastructure investments associated with a project;
(xiii) Allocation of project development
risks, including capital cost overruns, fuel price risk and environmental
regulatory risk among project developer, utility and ratepayers; and
(xiv) Environmental impacts.
(c) In developing the initial
screening and evaluation criteria, the Soliciting Utility, in consultation with
the Independent Evaluator (if then under contract) and the Division of Public
Utilities, shall consider the assumptions included in the Soliciting Utility's
most recent Integrated Resource Plan (IRP), any recently filed IRP Update, any
Commission order on the IRP or IRP Update and in its Benchmark
Option.
(d) The Soliciting Utility
may but is not required to consider non-conforming bids to the Request For
Qualifications (RFQ) or Request For Proposals (RFP). The Soliciting Utility
will provide advance notice to the Independent Evaluator of its decision
consider a non-conforming bid.
(3) Screening Criteria - Request for
Qualifications and Request of Proposals.
(a)
Prior to the deadline for responding to the RFP, the Soliciting Utility may
utilize a RFQ.
(b) The Independent
Evaluator will provide each of the bidders with a Bid number once the
Soliciting Utility, in consultation with the Independent Evaluator, has
determined that the bidder has met the criteria under the RFQ.
(c) Reasonable RFQ screening criteria may
include, but are not necessarily limited to, reasonable and nondiscriminatory
evaluation of the following factors:
(i)
Credit requirements and risk;
(ii)
Non-performance risk;
(iii)
Technical experience;
(iv)
Technical and financial feasibility; and
(v) Other reasonable screening criteria that
are applied in a fair, reasonable and nondiscriminatory manner.
(d) The RFQ should instruct each
potential bidder to state in its RFQ response whether it is an affiliate of the
Soliciting Utility or will contract with an affiliate of the Soliciting
Utility.
(4)
Disclosures. If a Solicitation includes a Benchmark Option, the Solicitation
shall include at least the following information and disclosures:
(a) Whether the Benchmark Option will or may
consist of a Soliciting Utility self-build or owned option (Owned Benchmark
Resource) or if it is a purchase option (Market Benchmark Resource);
(b) If an Owned Benchmark Option is used, a
description of the facility, fuel type, technology, efficiency, location,
projected life, transmission requirements and operating and dispatch
characteristics of the Owned Benchmark Option. If a Market Benchmark Option is
used, the Soliciting Utility must disclose that a market option will be
utilized and any inputs that will be utilized in the evaluation;
(c) A description and examples of the manner
in which resources of differing characteristics or lengths will be
evaluated;
(d) That bids will
receive Bid numbers from the Independent Evaluator. The blinded personnel will
not have access to any information concerning the relationship between the Bid
numbers and the Blinded bids until after selection of the final short
list;
(e) Assurances that resource
evaluations will be conducted in a fair and non-preferential manner in
comparison to the Benchmark Option;
(f) Assurances that the Benchmark Option will
be validated by the Independent Evaluator and that no changes to any aspect of
the Benchmark Option will be permitted after the validation of the Benchmark
Option by the Independent Evaluator and prior to the receipt of bids under the
RFP and that the Benchmark Option will not be subject to change unless updates
to other bids are permitted; and
(g) Assurances that the non-blinded personnel
will not share any non-blinded information about the bidders with employees or
agents of a Soliciting Utility or its affiliates who are or may be involved in
the development of a Solicitation, the evaluation of bids, or the selections of
resources (Evaluation Team) until after selection of the final
shortlist.
(5)
Disclosures Regarding Evaluation Methodology. A Solicitation shall include a
clear and complete description and explanation of the methodologies to be used
in the evaluation and ranking of bids, including a complete description of:
(a) All evaluation procedures, factors and
weights to be considered in the RFQ, initial screening and final evaluation of
bids;
(b) Credit and security
requirements;
(c) Pro forma power
purchase and other agreements; and
(d) The Solicitation schedule.
(6) Disclosures Regarding
Independent Evaluator. The Solicitation shall describe the Independent
Evaluator's role in a manner consistent with Section
54-17-203, including:
(a) An explanation of the role of the
Independent Evaluator;
(b) Contact
information for the Independent Evaluator; and
(c) Directions and encouragement for
potential bidders to contact the Independent Evaluator with any questions,
comments, information or suggestions.
(7) General Requirements. The Solicitation
Process must:
(a) Satisfy all applicable
requirements of the Act and Commission rules and be fair, reasonable and in the
public interest;
(b) Clearly
describe the nature and all relevant attributes of the requested
resources;
(c) Include clear
descriptions of the amounts and types of resources requested, the required
timing of deliveries, acceptable places of delivery, pricing options,
transmission constraints, requirements and costs that are known at the time,
scheduling requirements, qualification requirements, bid and selection formats
and procedures, price and non-price factors and weights, credit and security
requirements and all other information reasonably necessary to facilitate a
Solicitation Process in compliance with the Act and Commission rules;
(d) Utilize an evaluation methodology for
resources of different types and lengths which is fair, reasonable and in the
public interest and which is validated by the Independent Evaluator;
(e) Ensure that bidders will timely receive
the data and information determined by the Soliciting Utility, in consultation
with the Independent Evaluator or as directed by the Commission, to be
necessary to facilitate a fair and reasonable competitive bidding process and
all information reasonably requested by bidders;
(f) Impose credit requirements and other
participation and bidding requirements that are non- discriminatory, fair,
reasonable, and in the public interest;
(g) Permit a range of commercially reasonable
alternatives to satisfy credit and security requirements;
(h) Permit and encourage negotiation with
final short-list bidders for the benefit of ratepayers taking into account
increased value but also not unreasonably increasing risks to
ratepayers;
(i) Provide reasonable
protections for confidential information of bidders; subject to disclosure
pursuant to appropriate protective order to the Independent Evaluator and
otherwise as required by the Commission;
(j) Provide reasonable protections for
confidential information of the Soliciting Utility, subject to disclosure
pursuant to appropriate protective order to the Independent Evaluator and
otherwise as required by the Commission;
(k) Ensure that if any information that may
affect the Solicitation Process is to be shared by the Soliciting Utility with
any bidder or with the employees or agents of a Soliciting Utility or its
affiliates who may be involved in the development or submission of a Benchmark
Option used in a Solicitation (Bid Team), excluding confidential, proprietary
or competitively sensitive Benchmark- or bid-specific information or
negotiations, that the same information is shared with all bidders in the same
manner and at the same time.
(8) Process Requirements for Benchmark
Option. In a Solicitation Process involving the possibility of a Benchmark
Option:
(a) The Evaluation Team, including
non-blinded personnel, may not be members of the Bid Team, nor communicate with
members of the Bid Team during the Solicitation Process about any aspect of the
Solicitation Process, except as authorized herein.
(b) The names and titles of each member of
the Bid Team, the non-blinded personnel and Evaluation Team shall be provided
in writing to the Independent Evaluator.
(c) The Evaluation Team may solicit written
comments on matters of technical expertise from the members of the Bid Team.
All such communications to or from the Bid Team must be in writing. The
Independent Evaluator must participate in all such communications between
members of the Bid Team and Evaluation Team and must retain a copy of all such
correspondence to be made available in future Commission proceedings. The
Independent Evaluator must also make available to the bidder about whose bid
the Bid Team's technical expertise was sought a written copy of the
correspondence between the Evaluation and Bid Teams. Any response to such
correspondence from the bidder must be in writing to the Independent Evaluator
and must be conveyed to the Evaluation Team. The Independent Evaluator must
provide its own or third party verification of the reasonableness of any
technical information solicited from the Bid Team or bidder before it may be
used in any evaluation.
(d) There
shall be no communications regarding blinded bid information, either directly
or indirectly, between the non-blinded personnel and other Evaluation Team
members until the final shortlist is determined except as authorized herein,
which communications shall be done in the presence of the Independent
Evaluator. The non- blinded personnel must not reveal to other Evaluation Team
members, either directly or indirectly in any form, any blinded information
regarding the identity of any of the bidders.
(e) The Evaluation Team shall have no direct
or indirect contact or communication with any bidder other than through the
Independent Evaluator until such time as a final shortlist is selected by the
Soliciting Utility.
(f) Each member
of the Bid Team and Evaluation Team, including non-blinded personnel, shall
promptly execute a commitment and acknowledgment that he or she agrees to abide
by all of the restrictions and conditions contained in these Commission rules.
These acknowledgments shall be filed with the Commission within 10 days of
their execution.
(g) Should any
bidder or a member of the Bid Team attempt to contact a member of the
Evaluation Team, such bidder or member of the Bid Team shall be directed to the
Independent Evaluator for all information and such communication shall be
reported to the Independent Evaluator by the Evaluation Team within seven
business days.
(h) All relevant
costs and characteristics of the Benchmark Option must be audited and validated
by the Independent Evaluator prior to receiving any of the bids and are not
subject to change during the Solicitation except as provided herein.
(i) All bids must be considered and evaluated
against the Benchmark Option on a fair and comparable basis.
(j) Environmental risks and weight factors
must be applied consistently and comparably to all bid responses and the
Benchmark Option.
(k) The
Solicitation must allow power purchase contract terms equivalent to the
projected facility life of the Benchmark Option. The Commission may waive this
requirement during review of the draft Solicitation and Solicitation Process
for good cause shown.
(l) If the
Soliciting Utility is subject to regulation in more than one state concerning
the acquisition, construction, or cost recovery of a significant energy
resource, the Soliciting Utility shall explain the degree to which it has taken
into account the likelihood of resource approval and cost recovery in other
jurisdictions in exercising its judgment in selecting the Benchmark
Option.
(9) Issuance of
A Solicitation.
(a) The Soliciting Utility
shall issue the approved Solicitation promptly after Commission approval of the
Solicitation and Solicitation Process.
(b) Bidders shall be directed to submit bids
directly to the Independent Evaluator in accordance with the schedule contained
in the Solicitation.
(c) The
Soliciting Utility shall hold a pre-Bid conference in Utah, with both in-person
and conference call participation available, at least 30 days before the
deadline for submitting responsive bids.
(10) Evaluation of Bids.
(a) The Independent Evaluator shall "blind"
all bids and supply blinded bids to the Soliciting Utility and make blinded
bids available to the Division of Public Utilities subject to the provisions of
an appropriate Commission-issued protective order.
(b) The Independent Evaluator shall supply
such information regarding bidders and bids to non-blinded personnel as is
necessary to enable such personnel to complete required credit and legal
evaluations.
(c) The Soliciting
Utility must cooperate fully with the Independent Evaluator.
(d) Subject to an appropriate confidentiality
agreement approved by the Commission, the Soliciting Utility shall timely
provide to the Independent Evaluator and the Division of Public Utilities full
access to all relevant personnel of the Soliciting Utility, together with all
data, materials, models and other information, including confidential
information and forward pricing curves, used or to be used in developing the
proposed Solicitation, preparing the Benchmark Option, or screening, evaluating
or selecting bids.
(e) The
Soliciting Utility, monitored by the Independent Evaluator, shall conduct a
thorough evaluation of all bids in a manner consistent with the Act, Commission
Rules and the Solicitation.
(f) The
Independent Evaluator shall pursue a reasonable combination of auditing the
Soliciting Utility's evaluation and conducting its own independent evaluation,
in consultation with the Division of Public Utilities, such that the
Independent Evaluator can fulfill its duties and obligations as set forth in
the Act and in Commission Rules.
(g) The Soliciting Utility, the Division of
Public Utilities and the Independent Evaluator may request further information
from any bidder. Any communications with bidders in this regard shall be
conducted only through the Independent Evaluator. The Soliciting Utility shall
be informed in a timely manner of the content of any communications between the
Independent Evaluator and a bidder, but communications shall be conducted on a
confidential or blinded basis.
(h)
In order to facilitate both an independent evaluation function and an auditing
function, the Independent Evaluator shall have access to all information and
resources utilized by the Soliciting Utility in conducting its analyses. The
Soliciting Utility shall provide the Independent Evaluator with complete and
open access to all documents, information, data and models utilized by the
Soliciting Utility in its analyses. The Independent Evaluator shall be allowed
to actively and contemporaneously monitor all aspects of the Soliciting
Utility's evaluation process in the manner it deems appropriate so that the
Soliciting Utility's evaluation process is transparent to the Independent
Evaluator. The Soliciting Utility shall have an affirmative responsibility to
respond promptly and fully to any request for reasonable access or information
made by the Division of Public Utilities or the Independent Evaluator. To the
extent the Independent Evaluator determines through its audit or independent
evaluation that its evaluation and the Soliciting Utility's yield different
results, the Independent Evaluator shall notify the Soliciting Utility and the
Division of Public Utilities and attempt to identify reasons for the
differences as early as practicable. Where practicable, the Soliciting Utility,
the Division of Public Utilities and the Independent Evaluator shall attempt to
reconcile such differences. If the differences cannot be reconciled to the
Independent Evaluator's satisfaction, the Independent Evaluator will promptly
notify the Commission.
(i) The
Independent Evaluator shall be responsible for unblinding all bids included on
the final short-list and providing relevant contact information to the
Soliciting Utility for final negotiations with these short- listed bidders. The
Independent Evaluator shall monitor any negotiations with short-listed
bidders.
(j) The Division of Public
Utilities and the Independent Evaluator may, through the Independent Evaluator,
ask the PacifiCorp Transmission group to conduct reasonable and necessary
transmission analyses concerning bids received. Any such analyses shall be
provided to the Division of Public Utilities, the Independent Evaluator and the
Soliciting Utility. The Soliciting Utility may, in a general rate case or other
appropriate Commission proceeding, include and the Commission will allow,
recovery in the Soliciting Utility's retail rates of any reasonable amounts
paid by the Soliciting Utility for those analyses.