Section R655-4-15 - Monitor Well Construction Standards
Universal Citation: UT Admin Code R 655-4-15
Current through Bulletin 2024-18, September 15, 2024
15.1 Scope.
15.1.1 Certain construction standards that
apply to water wells also apply to monitor wells. Therefore, these monitoring
well standards refer frequently to the water well standard sections of this
rule. Standards that apply only to monitor wells, or that require emphasis, are
discussed in this section.
15.1.2
These standards are not intended as a complete manual for monitoring well
construction, alteration, maintenance, and abandonment. These standards serve
only as minimum statewide guidelines towards ensuring that monitor wells do not
constitute a significant pathway for the movement of poor quality water,
pollutants, or contaminants. These standards provide no assurance that a
monitor well will perform a desired function. Ultimate responsibility for the
design and performance of a monitoring well rests with the well owner or the
owner's contractor, or technical representatives. Most monitor well projects
are the result of compliance with the Environmental Protection Agency (EPA),
Federal Regulations such as the Resource Conservation and Recovery Act (RCRA),
Comprehensive Environmental Response, Compensation and Liability Act (CERCLA or
'Superfund"), or specific State Solid and Hazardous Waste requirements. The
contracts governing their installation are tightly written containing specific
requirements as to site location, materials used, sampling procedures and
overall objectives. Therefore, specific construction requirements for monitor
well installation shall be governed by applicable contracts and regulations
providing they meet or exceed state requirements and specifications. Guidelines
and recommended practices dealing with the installation of monitor wells may be
obtained from the state engineer upon request. Additional recommended
information may be obtained from the Environmental Protection Agency (EPA),
Resource Conservation and Recovery Act (RCRA), Groundwater Monitoring
Enforcement and Compliance Document available from EPA's regional office in
Denver, Colorado and from the Handbook of Suggested Practices for the Design
and Installation of Groundwater Monitoring Wells, available from the National
Groundwater Association in Dublin, Ohio.
15.2 Installation and Construction.
15.2.1 Materials and Equipment
Contaminant-Free. All material used in the installation of monitor wells shall
be contaminant-free when placed in the ground. Drilling equipment shall be
clean and contaminant-free in accordance with Subsection
R655-4-11 (11.6.4). During construction contaminated water should not be allowed to enter
contaminant-free geologic formations or water bearing zones.
15.2.2 Borehole Integrity. Some minor cross
contamination may occur during the drilling process, but the integrity of the
borehole and individual formations must then be safeguarded from permanent
cross connection.
15.2.3 Casing and
Screen. The well casing should be perforated or screened and filter packed with
sand or gravel where necessary to provide adequate sample collection at depths
where appropriate aquifer flow zones exist. The casing and screen selected
shall not affect or interfere with the chemical, physical, radiological, or
biological constituents of interest. Screens in the same well shall not be
placed across separate water bearing zones to minimize interconnection, aquifer
commingling, and cross contamination. Screens in a nested well can be placed in
separate water bearing zones as long as the intervals between the water bearing
zones are appropriately sealed and aquifer cross connection and commingling
does not occur. Monitor well casing and screen shall conform to ASTM standards,
or consist of at least 304 or 316 stainless steel, PTFE (Teflon), or Schedule
40 PVC casing.
15.2.4 Gravel or
Filter Pack. If installed, the gravel or filter pack should generally extend
two feet to ten feet above screened or perforated areas to prevent the
migration of the sealing material from entering the zones being sampled. Gravel
or filter pack material shall meet the requirements of Subsection
R655-4-11 (11.5.2). Gravel or filter pack for monitoring wells does not require
disinfection. Drill cutting should not be placed into the open borehole
annulus. The well driller shall ensure that a bridge or voids do not occur in
the annular space during the placement of the gravel pack by a sounding device
or other mechanism.
15.2.5 Annular
Seal. All monitor wells constructed shall have a continuous surface seal, which
seals the annular space between the borehole and the permanent casing, in
accordance with the provisions in Section
R655-4-11.
The surface seal depth requirements of Section
R655-4-11 do not apply to monitor wells. The surface seal may be more or less than 30
feet depending on the screen or perforation or gravel pack interval. Seals
shall also be constructed to prevent interconnection and commingling of
separate aquifers penetrated by the well, prevent migration of surface water
and contaminations into the well and aquifers, and shall provide casing
stability. The seal shall have a minimum diameter of four inches larger than
the nominal size of the permanent casing, and shall extend from land surface to
the top of the filter pack. After the permanent casing and optional filter pack
has been set in final position, a layer of bentonite or fine sand such as
mortar sand shall be placed on top of the filter pack to maintain separation
between the seal material and the screened interval to insure that the seal
placement will not interfere with the filter pack. The remaining annular space
shall be filled to land surface in a continuous operation with unhydrated
bentonite, neat cement grout, sand cement grout, or bentonite grout. Only
potable water should be used to hydrate any grout or slurry mixture. The
completed annular space shall fully surround the permanent casing, be evenly
distributed, free of voids, and extend from the permanent casing to undisturbed
or recompacted soil. All sealing materials and placement methods shall conform
to the standards in Section
R655-4-2 and
Subsection
R655-4-11 (11.4). The well driller shall ensure that a bridge or voids do not occur in
the annular space during the placement of the seal.
15.2.6 Cuttings, Decon Water, Development
Water, and Other IDW. Drill cuttings, decontamination (Decon) water, monitor
well development water, and other investigation derived waste (IDW) shall be
managed and disposed of in accordance with applicable state and federal
environmental regulations. It is the responsibility of the driller to know and
understand such requirements.
15.3 Minimum Surface Protection Requirements.
15.3.1 If a well is cased with metal and
completed above ground surface, a locking water resistant cap shall be
installed on the top of the well.
15.3.2 If the well is not cased with metal
and completed above ground surface, a protective metal casing shall be
installed over and around the well. The protective casing shall be cemented at
least two feet into the ground around the non-metallic casing. A water tight
cap shall be installed in the top of the well casing. A locking cap shall be
installed on the top of the protective casing.
15.3.3 Monitor wells completed above ground
and potentially accessible to vehicular damage shall be protected in the
following manner. At least three metal posts, at least three inches in
diameter, shall be cemented in place around the casing. Each post shall extend
at least three feet above and two feet below ground surface. A concrete pad may
be installed to add protection to the surface completion. If installed, the
concrete pad shall be at least four inches thick and shall slope to drain away
from the well casing. The base shall extend at least two feet laterally in all
directions from the outside of the well boring. When a concrete pad is used,
the well seal may be part of the concrete pad.
15.3.4 If the well is completed below land
surface, a water tight cap with a lock shall be attached to the top of the well
casing. A metal monument or equivalent shall be installed over and around the
well. The monument shall serve as a protective cover and be installed level
with the land surface and be equipped with a waterproof seal to prevent inflow
of any water or contaminants. Drains will be provided, when feasible, to keep
water out of the well and below the well cap. The monument and cover must be
designed to withstand the maximum expected load.
15.4 Abandonment.
15.4.1 Abandonment of monitor wells shall be
completed in compliance with Section
R655-4-14.
The requirements in Section
R655-4-14 are not required for the permanent abandonment of monitor wells completed at a
depth of 30 feet below natural ground surface.
Disclaimer: These regulations may not be the most recent version. Utah may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.