Rule R655-11 - Requirements for the Design, Construction and Abandonment of Dams
Section R655-11-4A - Inflow Design Hydrograph Determination

Universal Citation: UT Admin Code R 655-11-4A

Current through Bulletin 2024-18, September 15, 2024

A) In Utah, the IDF for all High and Moderate Hazard Dams will be the more critical SEF. It will be necessary to calculate both the 72 hour, general SEF using HMR49 with USUL as well as the 6 hour local SEF using HMR49 with USUS. These precipitation values need not exceed values calculated using HMR49 exclusively. Both of these hydrographs must be routed through the reservoir to determine which one represents the most extreme event.

B) Once the critical SEF has been determined, it must be compared to a flood generated by the 100 year, 6 hour (for local storms), or 100 yr, 24 hour (for general storms) precipitation applied on a saturated watershed. If the routed 100 year event, including appropriate allowances for freeboard, is more critical than the SEF it must be used as the minimum IDF. This 100 year flood should also be used as the IDF for all Low Hazard Dams.

Disclaimer: These regulations may not be the most recent version. Utah may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.