Utah Administrative Code
Topic - Natural Resources
Title R649 - Oil, Gas and Mining; Oil and Gas
Rule R649-5 - Underground Injection Control of Recovery Operations and Class II Injection Wells
Section R649-5-5 - Testing and Monitoring of Injection Wells
Current through Bulletin 2024-18, September 15, 2024
1. Before operating a new injection well, the casing shall be tested to a pressure not less than the maximum authorized injection pressure, or to a pressure of 300 psi, whichever is greater.
2. Before operating an existing well newly converted to an injection well, the casing outside the tubing shall be tested to a pressure not less than the maximum authorized injection pressure, or to a pressure of 1,000 psi, whichever is lesser, provided that each well shall be tested to a minimum pressure of 300 psi.
3. In order to demonstrate continuing mechanical integrity after commencement of injection operations, all injection wells shall be pressure tested or monitored as follows: