Utah Administrative Code
Topic - Natural Resources
Title R647 - Oil, Gas and Mining; Non-Coal
Rule R647-4 - Small Mining Operations
Section R647-4-113 - Surety
Current through Bulletin 2024-18, September 15, 2024
1. After receiving notification that the notice of intention has been approved, but prior to commencement of operations, the operator shall provide the reclamation surety to the Division. Failure to furnish and maintain reclamation surety may, after notice and opportunity for Board hearing, result in a withdrawal of the approved notice of intention as provided for in Section 40-8-16.
2. The Division will not require a separate surety when a reclamation surety in a form and amount acceptable to the Division is held by other governmental entities, provided that the cost estimate is accurate and the Division is named as co-beneficiary. Cooperative Agreements will be developed and entered into according to Section 40-8-22.
3. As part of the review of the notice of intention, the Division shall determine the final amount of surety required to reclaim the mine site. The surety amount will be based upon (a) the technical details of the approved mining and reclamation plan, (b) the proposed post mining land use, and (c) projected third party engineering and administrative costs to cover Division expenses incurred under a bond forfeiture circumstance. An operator's surety estimate will be accepted if it is accurate and verifiable. The Division may accept surety estimates based upon the Minerals Reclamation Program's average dollars per acre reclamation costs, if comparable to site specific cost estimates for similar operations.
4. The operator shall submit a completed Reclamation Contract (FORM MR-RC) with the required surety. The form and amount of the surety must be approved by the Division, except as provided in subpart 4.16. Acceptable forms may include:
5. Surety shall be required until such time as reclamation is deemed complete by the Division. The Division shall promptly conduct an inspection when notified by the operator that reclamation is complete. The full release of surety shall be evidence that the operator has reclaimed as required by the Act.
6. The amount of reclamation surety may be adjusted:
7. Notwithstanding any other provision of these rules, for operations where the surety is in the form of a Board-approved agreement under Section 40-8-14(3), the Board shall retain the sole authority over the release, partial release, revision or adjustment of the surety amount, if any, which shall be in accordance with the agreement and the Act.