Utah Administrative Code
Topic - Natural Resources
Title R647 - Oil, Gas and Mining; Non-Coal
Rule R647-4 - Small Mining Operations
Section R647-4-108 - Hole Plugging Requirements
Current through Bulletin 2024-18, September 15, 2024
Drill holes shall be properly plugged as soon as practical and shall not be left unplugged for more than 30 days without approval of the Division. The procedures outlined below are required for the surface and subsurface plugging of drill holes. The Division may approve an alternate plan, if the operator can prove to the satisfaction of the Division that another method will provide adequate protection to the groundwater resources and long term stability of the land. Dry holes and nonartesian holes which do not produce significant amounts of water may be temporarily plugged with a surface cap to permit the operator to re-enter the hole for the duration of operations.
1. Surface plugging of drill holes shall be accomplished by:
2. Drill holes that encounter water, oil, gas or other potential migratory substances and are 2-1/2 inches or greater in surface diameter shall be plugged in the subsurface to prevent the migration of fluid from one strata to another. If water is encountered, plugging shall be accomplished as outlined below:
2.11. If artesian flow (i.e., water flowing to the surface from the hole) is encountered during or upon cessation of drilling, a cement plug shall be placed to prevent water from flowing between geologic formations and at the surface. The cement mix should consist of API Class A or H cement with additives as needed. It should weigh at least 13.5 lbs./gal., and be placed under the supervision of a person qualified in proper drill hole cementing of artesian flow. Artesian bore holes must be plugged in the described manner, prior to removal of the drilling equipment from the well site. If the surface owner of the land affected desires to convert an artesian drill hole to a water well, he must notify the Division in writing that he accepts responsibility for the ultimate plugging of the drill hole.
2.12. Holes that encounter significant amounts of nonartesian water shall be plugged by: