Utah Administrative Code
Topic - Natural Resources
Title R647 - Oil, Gas and Mining; Non-Coal
Rule R647-2 - Exploration
Section R647-2-102 - Duration of the Notice of Intention

Universal Citation: UT Admin Code R 647-2-102

Current through Bulletin 2024-18, September 15, 2024

1. A Notice of Intention to Conduct Exploration that has been determined complete or, for operations of more than 5 10 acres has been approved, shall be valid until December 31st of the year following the year of submittal. All exploration and reclamation activities should be completed within this time frame. An operator desiring to extend the duration of a notice of intention, must notify the Division in writing, prior to expiration of the notice of intention, specifying the reasons an extension is required, and the anticipated length of time required to complete exploration and reclamation.

2. The Division will review and approve the extension and adjust if necessary, the amount of reclamation surety

3. Authorization to operate under a Notice of Intention to Conduct Exploration may be withdrawn in the event of failure by the operator to pay permit fees required by R647-2-101.6, or to maintain and update reclamation surety as required, after notice and opportunity for Board hearing.

Disclaimer: These regulations may not be the most recent version. Utah may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.