(1) Prior to construction, the floor plans, shielding specifications and equipment arrangement of all new installations, or modifications of existing installations, utilizing ionizing radiation shall be submitted to a Qualified Expert for review. The required information is denoted in R313-28-200 and R313-28-450.
(2) A copy of the Qualified Expert's conclusions regarding shielding specifications must be submitted to the Director within 14 working days.
(3) The Director may require additional modifications should a subsequent analysis of operating conditions, for example, a change in workload or use and occupancy factors, indicate the possibility of an individual receiving a dose in excess of the limits prescribed in R313-15.