Utah Administrative Code
Topic - Environmental Quality
Title R309 - Drinking Water
Rule R309-500 - Facility Design and Operation: Minimum Treatment Requirements
Section R309-500-9 - Operating Permit
Current through Bulletin 2024-24, December 15, 2024
(1) The Division shall be informed when a public drinking water project, or a well-defined phase thereof, is at or near completion.
(2) The new or modified facility shall not be placed into service until an Operating Permit is issued by the Director unless it meets the requirements of R309-500-7.
(3) The Operating Permit will not be issued until all of the following items are submitted and found to be acceptable for all projects.
(4) Distribution lines (not including in - line booster pump stations) requiring Plan Approval may be placed into service prior to submittal of all of the above items and receipt of an Operating Permit if the public water system has received items (3)(a) and (3)(d).