Utah Administrative Code
Topic - Capitol Preservation Board (State)
Title R131 - Administration
Rule R131-4 - Capitol Preservation Board General Procurement Rule
Section R131-4-416 - Cost-Plus-a-Percentage-of-Cost Contract

Universal Citation: UT Admin Code R 131-4-416

Current through Bulletin 2024-18, September 15, 2024

(1) Subject to the limitations of R131-4-416, any type of contract which will promote the best interests of the state or the Board may be used; provided that the use of a cost-plus-a-percentage-of-cost contract is only allowed as approved by the board, otherwise it is prohibited. A cost-reimbursement contract with a guaranteed maximum price may be used only when a determination is made in writing by the board that such contract is likely to be less costly to the state than any other type or that it is impracticable to obtain the supplies, services, or construction required except under such a contract.

(2) Except with respect to firm fixed-price contracts, no contract type shall be used unless it has been determined in writing by the executive director or the board that:

(a) the proposed contractor's accounting system will permit timely development of all necessary cost data in the form required by the specific contract type contemplated; and

(b) the proposed contractor's accounting system is adequate to allocate costs in accordance with generally accepted accounting principles.

Disclaimer: These regulations may not be the most recent version. Utah may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.