Utah Administrative Code
Topic - Administrative Services
Title R23 - Facilities Construction and Management
Rule R23-1 - Procurement Rules with Numbering Related to the Procurement Code
Section R23-1-713 - Best Value Analysis Exception: Construction Manager /General Contractor

Universal Citation: UT Admin Code R 23-1-713

Current through Bulletin 2024-06, March 15, 2024

(1) An evaluation committee is not required to explain how a recommended proposal provides the best value to the division under Section 63G-6a-707 if the contract is awarded solely on the qualifications of the construction manager/general contractor and the management fee described in Section 63G-6a-707 provided:

(a) a competitive process is maintained by the issuance of a request for proposals that requires the offeror to provide, at a minimum:
(i) a management plan;

(ii) references;

(iii) statements of qualifications; and

(iv) a management fee if requested by the division; and

(b) the management fee contains only the following:
(i) preconstruction phase services;

(ii) monthly supervision fees for the construction phase; and

(iii) overhead and profit for the construction phase.

(2) The evaluation committee may, as described in the solicitation, weight and score the management fee as a fixed rate or a fixed percentage of the estimated contract value.

(3) The management fee may not be requested by the division if the management fee is not part of the criteria for the evaluation committee. The division may use a fee table for this management fee.

(4) The contract awarded must be in the best interest of the division.

Disclaimer: These regulations may not be the most recent version. Utah may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.