(a) A property owner or its authorized representative, as the applicant, may file a petition of appeal to contest:
(b) A district engineer's denial of a request for an access permit under §11.59 of this subchapter (relating to Permit of Access at Locations Where the Department Owns the Access) is final and a property owner has no right to appeal the denial.
(c) The petition must be filed with the director before the 31st day after the date written notice of the denial, requirement, or finding is received by the applicant.
(d) The petition must:
(e) The applicant has the burden of demonstrating that the department incorrectly applied its access connection requirements to the applicable facts.
(f) For a petition that satisfies the requirements of this section, the director will issue, before the 91st day after the date of receipt of the petition, a written decision approving or disapproving the appeal and, on issuance, immediately send the decision to the applicant. If a written decision is not issued within the 90-day period, the appeal is considered to be approved and the request granted, subject to:
(g) To appeal a decision issued under subsection (f) of this section, the applicant must submit its written petition of appeal to the executive director before the 31st day after the date that written notice of the decision is received. The petition must satisfy the requirements of subsection (d) of this section. The executive director will issue, before the 31st day after the date of receipt of the petition, a written decision approving or disapproving the appeal.
(h) To appeal a decision of the executive director issued under subsection (g) of this section, the applicant must submit to the executive director its written petition of appeal to a board of variance, before the 31st day after the date that the executive director's decision under subsection (g) of this section is received. On receipt of the petition, the procedure set out in this subsection applies.