(a) Policy and purpose. This subchapter governs the environmental review of projects funded in whole or in part by the DWSRF. Environmental review of all proposed infrastructure projects is a condition of the use of DWSRF financial assistance and is subject to annual audits by the EPA. This subchapter follows the procedures established by the EPA for implementing the National Environmental Policy Act set forth at 40 CFR Part 6. The environmental review process described in this subchapter applies to the maximum extent legally and practicably feasible. However, the environmental review process may be modified due to an emergency condition as described in § 371.40(3) of this title (relating to Definitions). The environmental review is subject to public comment. The Applicant, at all times throughout the design, construction, and operation of the project, shall comply with the findings resulting from the environmental review.
(b) Timing. The environmental review process is a component of the planning phase and must be completed prior to the executive administrator's approval of the Applicant's engineering feasibility report.
(c) Types of environmental findings. At the culmination of the environmental review process described in this subchapter, the Board will issue one of the following findings :
(d) General review by the executive administrator.
(e) Equivalency projects. The Board will inform EPA when consultation or coordination by EPA with other federal agencies is necessary to resolve issues regarding compliance with applicable federal laws.