(a) Local Flood Planning Amendment Requests. A Political Subdivision in the FPR may request an RFPG to consider an amendment to an adopted RFP based on changed conditions or new information. An RFPG must formally consider such request within 180 days after its receipt and shall amend its adopted RFP if it determines an amendment is warranted.
(b) If the Political Subdivision is not satisfied with the RFPG's decision on the issue, it may file a petition with the EA to request review of the RFPG's decision and consider the amendment to the approved RFP. The Political Subdivision shall send the petition to the EA and the chair of the affected RFPG.
(c) Amendments to RFPs and State Flood Plan. An RFPG may amend an adopted, Board-approved RFP at a regular RFPG meeting. An RFPG must obtain Board approval of all amendments to RFPs under the standards and procedures of this section. The RFPG may initiate an amendment, or an entity may request an RFPG to amend its adopted, Board-approved RFP.
(d) All amendments to an RFP must meet all the requirements related to development of an RFP.
(e) Following amendments of RFPs, the Board shall make any necessary amendments to the State Flood Plan as outlined in § 362.4(b) of this title (relating to State Flood Plan Guidelines).
(f) RFPGs may adopt errata to the final RFP to correct minor, non-substantive errors identified after adoption of the final RFP but prior to adoption of the corresponding State Flood Plan. Before adopting errata to a final RFP, the RFPG must provide public notice and receive comments in accordance with § 361.21 of this title. Upon adoption of the errata, the RFPG shall submit to the EA an errata package containing revised pages of the RFP and public comments received. The EA will notify the RFPG within 60 days whether the errata are acceptable as errata or will need to be made through the amendment process.