Texas Administrative Code
Title 31 - NATURAL RESOURCES AND CONSERVATION
Part 10 - TEXAS WATER DEVELOPMENT BOARD
Chapter 357 - REGIONAL WATER PLANNING
Subchapter A - GENERAL INFORMATION
Section 357.12 - General Regional Water Planning Group Responsibilities and Procedures
Current through Reg. 49, No. 38; September 20, 2024
(a) Prior to the preparation for the RWPs, in accordance with the public participation requirements in § 357.21 of this title (relating to Notice and Public Participation), the RWPGs shall:
(b) In accordance with the requirements of § 357.21(g)(2) of this title, an RWPG shall hold a public meeting to determine the process for identifying potentially feasible WMSs; the process shall be documented and shall include input received at the public meeting; after reviewing the potentially feasible strategies using the documented process, then the RWPG shall list all possible WMSs that are potentially feasible for meeting a Water Need in the region. The public meeting shall also include a presentation of the results of the analysis of infeasible WMSs or WMSPs, as defined by Texas Water Code § 16.053(h)(10), included in the most recently adopted RWP. Infeasible WMSs or WMSPs shall be identified based on project sponsor provided information or local knowledge, as acquired through plan development activities such as surveys, and as determined based on implementation schedules consistent with implementation by the project sponsors. The group shall provide notice to all associated project sponsors and amend its adopted RWP as appropriate based upon the analysis.
(c) The RWPGs shall approve and submit a Technical Memorandum to the EA after notice pursuant to § 357.21(g)(2) of this title. The Technical Memorandum shall include:
(d) The EA shall evaluate the Technical Memorandum and any declaration of intent to pursue simplified planning, if applicable, and issue written approval prior to implementation of simplified planning by the RWPG. If an RWPG has not declared to pursue simplified planning in their Technical Memorandum, they may proceed without any additional approvals to develop their IPP. If the RWPG chooses to rescind their decision to pursue simplified planning, they must do so prior to executing a contract scope of work and budget amendment with the TWDB. The RWPG must discuss and act on the decision at a public meeting posted under notice requirements of § 357.21(g)(1) of this title.
(e) If applicable, and approved by the EA, an RWPG may implement simplified planning in off-census planning cycles in accordance with guidance to be provided by the EA. An RWPG may only pursue simplified planning if:
(f) If an RWPG elects to pursue simplified planning, it must:
(g) If an RWPG declares intention to pursue simplified planning with the submittal of its Technical Memorandum, in accordance with subsection (c) of this section, the RWPG shall hold a public hearing on the intent to pursue simplified planning for the RWPA, to be held after submitting the Technical Memorandum and in accordance with § 357.21(g)(3) of this title. This public hearing is not required for RWPGs that state they will not pursue simplified planning in their Technical Memorandum.
(h) Following receipt of public comments, the RWPG shall hold a meeting in accordance with the requirements of § 357.21(g)(1) of this title to consider comments received and declare implementation of simplified planning.
(i) Each RWPG and any committee or subcommittee of an RWPG are subject to Chapters 551 (relating to Open Meetings) and 552 (relating to Public Information), Government Code.