Section 336.1115 - Expiration and Termination of Licenses; Decommissioning of Sites, Separate Buildings or Outdoor Areas
Current through Reg. 50, No. 13; March 28, 2025
(a) The term of the specific license is for a fixed term not to exceed ten years.
(b) Expiration of the specific license does not relieve the licensee of the requirements of this chapter.
(c) All license provisions continue in effect beyond the expiration date with respect to possession of radioactive material until the agency notifies the former licensee in writing that the provisions of the license are no longer binding. During this time, the former licensee must:
(d) Within 60 days of the occurrence of any of the following, each licensee must provide notification to the agency in writing and either begin decommissioning its site, or any separate buildings or outdoor areas that contain residual radioactivity in accordance with the closure plan in § 336.1111(1)(B) of this title (relating to Special Requirements for a License Application for Source Material Recovery and By-product Material Disposal Facilities), so that the buildings or outdoor areas are suitable for release in accordance with subsection (e) of this section if:
(e) Outdoor areas are considered suitable for release for unrestricted use if the following limits are not exceeded.
(f) Coincident with the notification required by subsection (c) of this section, the licensee shall maintain in effect all decommissioning financial security established by the licensee in accordance with § 336.1125 of this title (relating to Financial Assurance Requirements) in conjunction with a license issuance or renewal or as required by this section. The amount of the financial security must be increased, or may be decreased, as appropriate, with agency approval, to cover the detailed cost estimate for decommissioning established in accordance with subsection (l)(5) of this section.
(g) In addition to the provisions of subsection (h) of this section, each licensee must submit an updated closure plan to the agency within 12 months of the notification required by subsection (d) of this section. The updated closure plan must meet the requirements of § 336.1111(1)(B) and § 336.1125 of this title. The updated closure plan must describe the actual conditions of the facilities and site and the proposed closure activities and procedures.
(h) The agency may grant a request to delay or postpone initiation of the decommissioning process if the agency determines that such relief is not detrimental to the occupational and public health and safety and is otherwise in the public interest. The request must be submitted no later than 30 days before notification in accordance with subsection (d) of this section. The schedule for decommissioning in subsection (d) of this section may not begin until the agency has made a determination on the request.
(i) A decommissioning plan must be submitted if required by license condition or if the procedures and activities necessary to carry out decommissioning of the site or separate building or outdoor area have not been previously approved by the agency and these procedures could increase potential health and safety impacts to workers or to the public, such as in any of the following cases:
(j) The agency may approve an alternate schedule for submittal of a decommissioning plan required in accordance with subsection (d) of this section if the agency determines that the alternative schedule is necessary to the effective conduct of decommissioning operations and presents no undue risk from radiation to the occupational and public health and safety and is otherwise in the public interest.
(k) The procedures listed in subsection (i) of this section may not be carried out prior to approval of the decommissioning plan.
(l) The proposed decommissioning plan for the site or separate building or outdoor area must include:
(m) The proposed decommissioning plan may be approved by the agency if the information in the plan demonstrates that the decommissioning will be completed as soon as practicable and that the occupational health and safety of workers and the public will be adequately protected.
(n) Except as provided subsection (p) of this section, licensees shall complete decommissioning of the site or separate building or outdoor area as soon as practicable but no later than 24 months following the initiation of decommissioning.
(o) Except as provided in subsection (p) of this section, when decommissioning involves the entire site, the licensee must request license termination as soon as practicable but no later than 24 months following the initiation of decommissioning.
(p) The agency may approve a request for an alternate schedule for completion of decommissioning of the site or separate buildings or outdoor areas and the license termination if appropriate, if the agency determines that the alternative is warranted by the consideration of the following:
(q) As the final step in decommissioning, the licensee must:
(r) The executive director will provide written notification to specific licensees, including former licensees with license provisions continued in effect beyond the expiration date in accordance with subsection (d) of this section, that the provisions of the license are no longer binding. The executive director will provide such notification when the executive director determines that:
(s) Licenses for source material recovery or by-product material disposal are exempt from subsections (d)(3), (g), and (h) of this section with respect to reclamation of by-product material impoundments or disposal areas. Timely reclamation plans for by-product material disposal areas must be submitted and approved in accordance with § 336.1129(p) - (aa) of this title (relating to Technical Requirements).
(t) A licensee may request that a subsite or a portion of a licensed site be released for unrestricted use before full license termination as long as release of the area of concern will not adversely impact the remaining unaffected areas and will not be recontaminated by ongoing authorized activities. When the licensee is confident that the area of concern will be acceptable to the agency for release for unrestricted use, a written request for release for unrestricted use and agency confirmation of closeout work performed shall be submitted to the agency. The request should include a comprehensive report, accompanied by survey and sample results that show contamination is less than the limits specified in subsection (e) of this section and an explanation of how ongoing authorized activities will not adversely affect the area proposed to be released. Upon confirmation by the agency that the area of concern is releasable for unrestricted use, the licensee may apply for a license amendment, if required.