Texas Administrative Code
Title 30 - ENVIRONMENTAL QUALITY
Part 1 - TEXAS COMMISSION ON ENVIRONMENTAL QUALITY
Chapter 331 - UNDERGROUND INJECTION CONTROL
Subchapter F - STANDARDS FOR CLASS III WELL PRODUCTION AREA DEVELOPMENT
Section 331.107 - Restoration
Current through Reg. 50, No. 13; March 28, 2025
(a) Aquifer restoration. Groundwater in the production zone within the production area must be restored when mining is complete. Each Class III permit or production area authorization shall contain a description of the method for determining that groundwater has been restored in the production zone within the production area. Restoration must be achieved for all values in the restoration table of all parameters in the suite established in accordance with the requirements of § 331.104(b) of this title (relating to Establishment of Baseline and Control Parameters for Excursion Detection).
(b) Mining completion. When the mining of a permit or production area is completed, the permittee shall notify the appropriate commission regional office and the executive director and shall proceed to reestablish groundwater quality in the affected permit or production area aquifers in accordance with the requirements of subsection (a) of this section. Restoration efforts shall begin as soon as practicable but no later than 30 days after mining is completed in a particular production area. The executive director, subject to commission approval, may grant a variance from the 30-day period for good cause shown.
(c) Timetable. Aquifer restoration, for each permit or production area, shall be accomplished in accordance with the timetable specified in the currently approved mine plan, unless otherwise authorized by the commission. Authorization for expansion of mining into new production areas may be contingent upon achieving restoration progress in previously mined production areas within the schedule set forth in the mine plan. The commission may amend the permit to allow an extension of the time to complete restoration after considering the following factors:
(d) Reports. Beginning six months after the date of initiation of restoration of a permit or production area, as defined in the mine plan, and until receiving written acknowledgment from the executive director that restoration for the production areas has been accomplished, the operator shall provide to the executive director semi-annual restoration progress reports. This report shall contain the following information:
(e) Restoration table values achieved. When the permittee determines that constituents in the aquifer have been restored to the values in the Restoration Table, the restoration shall be demonstrated by stability sampling in accordance with subsection (f) of this section.
(f) Stability sampling. The permittee shall obtain stability samples and complete an analysis for all parameters listed in the restoration table from all production area baseline wells. Stability sampling may commence 60 days after cessation of restoration operations. Stability samples shall be conducted at a minimum of 30-day intervals for a minimum of three sample sets and reported to the executive director. The permittee shall notify the executive director at least two weeks in advance of sample dates to provide the opportunity for splitting samples and for selecting additional wells for sampling, if desired. To ensure water quality has stabilized, a period of one calendar year must elapse between cessation of restoration operations and the final set of stability samples. Upon acknowledgment in writing by the executive director confirming achievement of final restoration, the permittee shall accomplish closure of the area in accordance with § 331.86 of this title (relating to Closure).
(g) Amendment of restoration table or range table values. After an appropriate effort has been made to achieve restoration in accordance with the requirements of subsection (a) of this section, the permittee may cease restoration operations, reduce bleed and request that the restoration table be amended. With the request for amendment of the restoration table values, the permittee shall submit stability sampling results in accordance with subsection (f) of this section. The permittee shall notify the executive director of his or her intent to cease restoration operations and reduce the bleed 30 days prior to implementing these steps. If any restoration table value for any parameter listed in the restoration table will exceed the maximum value for the respective parameter in the permit range table, the permittee must submit an application for a major amendment of the permit range table.