(a) Casing and cementing. All new Class III wells, baseline wells, and monitor wells associated with the mining operations shall be cased, cemented from the bottom of the casing to the surface, and capped to prevent the migration of fluids which may cause the pollution of underground sources of drinking water (USDWs) and maintained in that condition throughout the life of the well. In addition, existing wells in areas where there is the potential for contamination and other harmful or foreign matter to enter groundwater through an open well, shall also be cemented to the surface and capped. The casing and cement used in the construction of each well shall be designed for the life expectancy of the well. In determining and specifying casing and cementing requirements, the following factors shall be considered:
(b) Alterations to construction plans. Any proposed changes or alterations to construction plans after permit issuance shall be submitted to the executive director and written approval obtained before incorporating such changes.
(c) Logs and tests. Appropriate logs and other tests shall be conducted during the drilling and construction of all new Class III wells and after an existing well has been repaired. A descriptive report interpreting the results of those logs and tests shall be prepared by a knowledgeable log analyst and submitted to the executive director. The logs and tests appropriate to each type of Class III well shall be determined based on the intended function, depth, construction, and other characteristics of the well, availability of similar data in the area of the drilling site, and the need for additional information that may arise from time to time as the construction of the well progresses.
(d) Construction and testing supervision. All phases of well construction and testing shall be supervised by a person who is knowledgeable and experienced in practical drilling engineering and who is familiar with the special conditions and requirements of injection well construction.
(e) Injection zone characteristics - water bearing formation. Where the injection zone is a water bearing formation, the following information concerning the injection zone shall be determined or calculated:
(f) Injection zone characteristics - non-water bearing formations. Where the injection formation is not a water bearing formation, the fracture pressure shall be determined or calculated.
(g) Monitor well location. Where injection is into a formation which contains water with less than 10,000 milligrams per liter of total dissolved solids, monitoring wells shall be completed into the injection zone and into any USDW above the injection zone which could be affected by the mining operation. These wells shall be located to detect any excursion of injection fluids, production fluids, process by-products, or formation fluids outside the mining area or zone. If the operation may be affected by subsidence or catastrophic collapse, the monitoring wells shall be located so that they will not be physically affected. Designated monitoring wells shall be installed at least 100 feet inside any permit area boundary, unless excepted by written authorization from the executive director.
(h) Subsidence or catastrophic collapse. Where the injection wells penetrate a USDW in an area subject to subsidence or catastrophic collapse an adequate number of monitor wells shall be completed into the USDW to detect any movement of injected fluids, process by-products or formation fluids into the USDW. The monitor wells shall be located outside the physical influence of the subsidence or catastrophic collapse.
(i) Monitor well criteria. In determining the number, location, construction, and frequency of monitoring of the monitor wells the following criteria shall be considered: