(b) Pre-operation reports. For new wells, including wells converting to Class I status, the requirements are as follows.
(1) Completion report. Within 90 days after the completion or conversion of the well, the permittee shall submit a Completion Report to the executive director. The report must include a surveyor's plat showing the exact location and giving the latitude and longitude of the well. The report must also include a certification that a notation on the deed to the facility property or on some other instrument which is normally examined during title search has been made stating the surveyed location of the well, the well permit number, and its permitted waste streams. The permittee shall also include in the report the following, prepared and sealed by a licensed professional engineer or licensed professional geoscientist with current registration under the Texas Engineering Practice Act or Texas Geoscience Practice Act:
(A) actual as-built drilling and completion data on the well;
(B) all logging and testing data on the well;
(C) a demonstration of mechanical integrity;
(D) anticipated maximum pressure and flow rate at which the permittee will operate;
(E) results of the injection zone and confining zone testing program as required in §
331.62 of this title (relating to Construction Standards) and this subsection;
(F) adjusted formation pressure increase calculations, fluid front calculations and updated cross-sections of the confining and injection zones, based on the data obtained during construction and testing;
(G) the actual injection procedure;
(H) the compatibility of injected wastes with fluids in the injection zone and minerals in both the injection zone and the confining zone and materials used to construct the well;
(I) the calculated area of review and cone of influence based on data obtained during logging and testing of the well and the formation, and where necessary, revisions to the information submitted under §
331.121 of this title (relating to Class I Wells);
(J) the status of corrective action required for defective wells in the area of review;
(K) a Well Data Report on forms provided by the executive director;
(L) compliance with the casing and cementing performance standard in §
331.62(5) of this title; and
(M) compliance with the cementing requirements in §
331.62(6) of this title.
(2) Local authorities. The permittee shall provide written notice to the executive director, in a manner specified by the executive director, that a copy of the permit has been properly filed with the health and pollution control authorities of the county, city, and town where the well is located.
(3) Start-up date and time. The permittee shall notify the executive director in writing of the anticipated well start-up date. Compliance with all pre-operation terms of the permit must occur prior to beginning injection operations. The permittee shall notify the executive director at least 24 hours prior to beginning drilling operations.
(4) Approval of construction and completion. Prior to beginning operations, the permittee must obtain written approval from the executive director, according to §
331.45 of this title (relating to Executive Director Approval of Construction and Completion).