Texas Administrative Code
Title 30 - ENVIRONMENTAL QUALITY
Part 1 - TEXAS COMMISSION ON ENVIRONMENTAL QUALITY
Chapter 321 - CONTROL OF CERTAIN ACTIVITIES BY RULE
Subchapter B - CONCENTRATED ANIMAL FEEDING OPERATIONS
Section 321.33 - Applicability and Required Authorizations
Current through Reg. 50, No. 13; March 28, 2025
(a) Permit required. All concentrated animal feeding operations (CAFOs) are point sources that require owners and operators to seek and obtain authorization under a water quality general permit or individual permit, except as provided in subsection (f) of this section. CAFO owners and operators have a duty to seek coverage as described in this section.
(b) Individual permit required. A discharge from the following CAFOs may be authorized only under an individual water quality permit in accordance with § 321.34 of this title (relating to Permit Applications). Except as provided by subsection (f) of this section, any operator who is required to obtain an individual water quality permit under this subsection may not commence physical construction and/or operation of any new control facilities until an individual water quality permit is issued for that CAFO, or unless otherwise authorized by the commission in accordance with Texas Water Code (TWC), §26.027(c).
(c) Individual permit or general permit required. A discharge from any other CAFO shall be authorized either by an individual water quality permit or an applicable CAFO general permit. Except as provided by subsection (f) of this section, any operator required to obtain an individual water quality permit or authorization under a CAFO general permit according to this subsection may not begin physical construction or operation of any new control facility until the CAFO operator receives an individual water quality permit or authorization under a CAFO general permit, unless otherwise authorized by the commission under TWC, §26.027(c).
(d) New or expanding AFO. No person may commence construction or operation of a new CAFO or alter any existing AFO such that it becomes defined as a CAFO without prior authorization through an individual water quality permit or a CAFO general permit, unless otherwise authorized by the commission under TWC, §26.027(c). This subsection does not apply to dry litter poultry operations specified in subsection (f) of this section.
(e) Newly defined CAFO. An existing AFO that becomes classified as a CAFO may not begin physical construction or operation of any new control facility until the CAFO operator receives authorization through an individual water quality permit or a CAFO general permit, unless otherwise authorized by the commission under TWC, §26.027(c).
(f) Dry litter poultry operations. A dry litter poultry CAFO shall only be required to obtain authorization by an individual water quality permit or a CAFO general permit in accordance with subsection (a), (b), or (c) of this section if it proposes to discharge or the executive director determines that a permit is necessary due to an unauthorized discharge; the operation's failure to comply with, or timely obtain, a certified water quality management plan approved by the Texas State Soil and Water Conservation Board; or other pertinent factors. Any dry litter poultry CAFO is authorized to be constructed and operated if the operation has a certified water quality management plan approved by the Texas State Soil and Water Conservation Board or is otherwise in compliance with the plan implementation schedule set forth in the notes following codified TWC, §26.302.
(g) Expansion or modification requirements. A CAFO operator authorized under an individual water quality permit shall comply with § 305.62 of this title (relating to Amendments). Before the permittee begins physical construction or operation of any new control facility, the operator must obtain commission authorization. Changes for which an individual permit amendment is required include, but are not limited to:
(h) AFOs that are not defined or designated as CAFOs. Discharges of manure, sludge, or wastewater from an AFO that is not a CAFO as defined in this subchapter are authorized under this subchapter. Requirements applicable to these AFOs are described in § 321.47 of this title (relating to Requirements for Animal Feeding Operations (AFOs) Not Defined or Designated As Concentrated Animal Feeding Operations (CAFOs)).
(i) Edwards Aquifer. New CAFOs are prohibited within the Edwards Aquifer recharge zone.
(j) Permit term. Individual and general permits issued under this subchapter shall be effective for a term not to exceed five years from the date the permit is issued.
(k) Dual authorization. No person may concurrently hold both an individual water quality permit and authorization under a CAFO general permit for the same CAFO.
(l) Additional requirements. Authorization under this subchapter, a general permit, or an individual permit does not release the operator from any responsibilities or requirements under other federal, state, or local statutes or regulations.
(m) State-only authorizations. Any AFO that is a state-only CAFO shall be authorized in accordance with subsection (a), (b), or (c) of this section.