Section 293.81 - Change Orders
Current through Reg. 50, No. 13; March 28, 2025
A change order is a change in plans, specifications, or scope of work for construction work that is under contract. For purposes of this section, a variation between estimated quantities and actual quantities or use of supplemental items included in the bid where no change in plans and specifications has occurred is not a change order.
(1) Districts are authorized to issue change orders that are necessary or beneficial to the district as determined by the district's board, which alter the plans, specifications, or scope of work in the contract, subject to the following conditions.
(2) No commission approval is required if the change order is $50,000 or less. If the change order is more than $50,000, the executive director or his designated representative may approve the change order. For purposes of this section, if either the total additions or total deletions contained in the change order exceed $50,000, even though the net change in the contract price will be $50,000 or less, approval by the executive director is required.
(3) If the change order is $50,000 or less, a copy of the change order signed by the contractor and an authorized representative of the district shall be submitted to the executive director within ten days of the execution date of the change order, together with any revised construction plans and specifications approved by all agencies and entities having jurisdictional responsibilities, i.e., city, county, state, other, if required.
(4) Applications for change orders requiring approval shall include:
(5) Copies of all changes in plans, specifications, and supporting documents for all water district projects will be sent directly to the appropriate commission field office, simultaneously with the submittal of the documents to the executive director.
(6) Requirements relating to change orders shall also apply to construction carried out in accordance with § 293.46 of this title (relating to Construction Prior to Commission Approval), except commission approval or disapproval will not be given. Change orders which are subject to executive director approval will be evaluated during the bond application review.