Current through Reg. 49, No. 38; September 20, 2024
(a) General provisions. DSHS must be notified
using DSHS's online asbestos notification system on its website or on a form
specified by DSHS of any asbestos abatement or demolition, as required in
paragraphs (1) and (2) of this subsection. Notification must be made to DSHS no
fewer than 10 working days before commencement of the activity. Submitting the
notification form online on DSHS's website or by hard copy meets the
requirements for notification to DSHS under both NESHAP and this chapter. The
notification form must be properly completed and submitted as required in this
section.
(1) Public buildings. DSHS must be
notified of any demolition of a public building whether or not asbestos has
been identified. DSHS must be notified of any asbestos abatement within a
public building. Notification must be submitted as required in this
section.
(2) Facilities. For all
facilities, including commercial buildings that are not otherwise subject to
this chapter as public buildings, DSHS must be notified of any demolition of a
facility, whether or not asbestos has been identified. DSHS must be notified of
any renovation operation if the combined amount of RACM to be stripped,
removed, dislodged, cut, drilled, or similarly disturbed meets or exceeds the
NESHAP threshold, in accordance with
40 CFR §
61.145 (relating to Standard for demolition
and renovation) of 160 square feet of surface area, 260 linear feet of pipe
length, or 35 cubic feet off facility components where the length or area could
not be measured. Notification must be submitted in accordance with
NESHAP.
(b)
Responsibility for proper notification.
(1)
Public buildings. It is the responsibility of the public building owner and
delegated agent (such as a licensed asbestos abatement contractor, asbestos
consultant, or demolition contractor) to submit a notification to DSHS for each
project. When the task to notify is delegated, the building owner's delegation
and the name of the delegated agent must be specified on the notification form.
The building owner and the delegated agent are responsible for the accuracy and
timeliness of the notification and one or both may be found in violation for
failing to accurately and timely notify DSHS of a project.
(2) Facilities. It is the responsibility of
the facility owner or operator to submit a notification to DSHS for each
project. The facility owner and operator are responsible for the accuracy and
timeliness of the notification and one or both may be found in violation for
failing to accurately and timely notify DSHS of a project.
(c) Completion of the notification form. The
DSHS notification form must be fully and properly completed.
(1) No applicable form field as specified on
the notification form and notification instructions may be left blank and form
fields must contain accurate information. Form fields that are not applicable
must be marked "NA." The fields on the form for the work site, building
description, building owner, abatement and waste transportation companies, and
start and stop dates and times must be filled in. Use of the designation "NA"
for any of these fields does not comply with the requirements of this section
or 40 CFR §
61.145 (relating to Standard for demolition
and renovation).
(2) The building
owner or the delegated agent must submit an amendment to the notification for
any changes. This includes changes to the start and stop dates, phased schedule
form, amounts of asbestos to be removed, and cancellations. An amendment is not
required if the amount of asbestos to be removed changes by less than
20%.
(3) A hard copy notification
form must contain an original signature. DSHS does not accept a copied
signature.
(d) Submission
of the notification form and an amendment to the notification.
(1) The notification form and an amendment to
the notification must:
(A) be submitted
online on DSHS's website;
(B) be
postmarked and delivered by the United States Postal Service (USPS);
(C) be date-stamped and delivered by
commercial delivery service; or
(D)
be delivered by hand during normal business hours.
(2) Printed notification forms must not be
submitted by fax or email.
(e) Timeliness of an initial notification and
an amendment to the notification.
(1) The
initial notification of asbestos abatement or demolition must be submitted to
DSHS at least 10 working days before the asbestos abatement or demolition start
date. If the initial notification is for both asbestos abatement and
demolition, the initial notification must be submitted 10 working days before
either the asbestos abatement or demolition start date, whichever is
earliest.
(2) If a project start
date, stop date, phased project schedule, scheduled work day, or time changes
from the current notified date, schedule, scheduled work day, or time, an
amended notification must be submitted to DSHS, as required in subsections
(f)-(j) and (q)(2) of this section.
(f) Start date change to an earlier date.
When asbestos abatement or demolition will begin on a date earlier than the
date in the notification:
(1) an amended
notification must be submitted to DSHS at least 10 working days before the new
start date, as required in subsection (d) of this section;
(2) the appropriate DSHS regional office must
be provided with a fax or email copy of the amended notification at least 10
working days before the new start date; and
(3) for notifications not submitted online,
the appropriate DSHS regional office must also be contacted by phone at least
10 working days before the new start date.
(g) Stop date change to an earlier date. An
amendment is required for a stop date that changes to an earlier date unless
the stop date changes by one working day for every seven calendar days of
scheduled work in the notification but does not change by more than seven
working days from the notified stop date. This provision does not grant an
extension of time to amend the notification. When asbestos abatement or
demolition ends on a date earlier than the date in the notification:
(1) an amended notification of the new stop
date must be submitted as required in subsection (d) of this section to DSHS as
soon as possible, but no later than the new stop date;
(2) the appropriate DSHS regional office must
be provided with a fax or email copy of the amended notification as soon as
possible, but no later than the new stop date; and
(3) for notification not submitted online,
the appropriate DSHS regional office must also be contacted by phone of the new
stop date as soon possible, but no later than the new stop date.
(h) Start date change to a later
date. When asbestos abatement or demolition will begin later than the date in
the notification:
(1) an amended notification
with the new start date must be submitted as required in subsection (d) of this
section to DSHS as soon as possible, but no later than the current notified
start date;
(2) the appropriate
DSHS regional office must be provided with a fax or email copy of the amended
notice as soon as possible, but no later than the current notified start date;
and
(3) for notification not
submitted online, the appropriate DSHS regional office must also be contacted
by phone of the new start date as soon as possible, but no later than the
current notified start date.
(i) Stop date change to a later date. An
amendment is required for a stop date that changes to a later date unless the
stop date changes by one working day for every seven calendar days of scheduled
work in the notification but does not change by more than seven working days
from the notified stop date. This provision does not grant an extension of time
to amend the notification. When asbestos abatement or demolition will end on a
date later than the current notified stop date:
(1) an amended notification of the new stop
date must be submitted as required in subsection (d) of this section to DSHS as
soon as possible, but no later than the current notified stop date;
(2) the appropriate DSHS regional office must
be provided with a fax or email copy of the amended notice as soon as possible,
but no later than the current notified stop date; and
(3) for notification not submitted online,
the appropriate DSHS regional office must also be contacted by phone of the new
stop date as soon as possible, but no later than the current notified stop
date.
(j) Cancellation.
(1) When asbestos abatement or demolition is
cancelled, the building owner or the delegated agent must:
(A) submit a notice of the cancellation as
required in subsection (d) of this section to DSHS as soon as possible, but no
later than the current notified start date;
(B) the appropriate DSHS regional office must
be provided with a fax or email copy of the notice of cancellation as soon as
possible, but no later than the current notified start date; and
(C) the appropriate DSHS regional office must
also be contacted by phone of the cancellation as soon as possible, but no
later than the current notified start date.
(2) When asbestos abatement and demolition
are both notified on the same notification, and either the abatement or
demolition will not occur, an amendment must be submitted to remove the
abatement or demolition activity that will not occur on or before the notified
start date for that activity.
(k) Consolidated notification of nonscheduled
asbestos O&M activities in a public building.
(1) Notification of a series of nonscheduled,
separate O&M activities involving ACBM, each of which does not meet or
exceed a threshold of 160 square feet of surface area, 260 linear feet of pipe
length, or 35 cubic feet volume off facility components where the length or
area could not be measured previously, may be made annually. An individual
project that meets or exceeds this threshold must be notified separately and
must not be notified as part of the consolidated notification. The consolidated
notification must include a prediction of the cumulative amount of asbestos to
be removed, enclosed, or encapsulated from January 1 through December 31 of the
calendar year for which consolidated notification is being given. Consolidated
notifications must be submitted at least 10 working days before the calendar
year for which notification is being given for a single building, or for a
group of public buildings at one site under the control of one owner or
operator. Consolidated notification must be submitted as required in subsection
(d) of this section.
(2) The
building owner or delegated agent must notify the appropriate DSHS regional
office by fax or email before each O&M activity for which notification is
given in a consolidated notification under this subsection.
(3) The building owner must keep records of
the individual O&M activities. If, at any point during the calendar year
for which consolidated notification was given, the amount of asbestos removed,
enclosed, or encapsulated changes from the notified amount by 20% or more, an
amendment must be submitted within 10 working days thereafter.
(l) Consolidated notification of
nonscheduled renovation operations in a facility that is not a public building.
(1) A notification is required when the
combined amount of RACM for planned renovation operations involving individual
nonscheduled renovation operations, such as renovations resulting from
equipment failure, meets or exceeds the NESHAP threshold of 160 square feet of
surface area, 260 linear feet of pipe length, or 35 cubic feet off facility
components where the length or area could not be measured. To determine whether
notification is required, the facility owner or operator must predict the
combined additive amount of RACM to be removed from January 1 to December 31 of
the calendar year for which consolidated notification is being given. These
operations may be notified on a single consolidated notification form for each
facility for which a consolidated notification is required under this
paragraph. Consolidated notifications must be submitted at least 10 working
days before the calendar year for which notice is being given. Consolidated
notification must be submitted as required in subsection (d) of this
section.
(2) Upon request by DSHS,
the facility owner or operator must be able to demonstrate that the amount of
RACM stripped or removed did not change from the notified amount by 20% or
more. If, at any point during the calendar year for which consolidated
notification was given, the amount of RACM stripped or removed changes from the
notified amount by 20% or more, an amendment must be submitted within 10
working days thereafter.
(3) If the
facility owner or operator determines that the NESHAP threshold amount will be
exceeded and a consolidated notification was not previously submitted under
this subsection, a notification must be submitted at least 10 working days
before the start date of the activity that will exceed the threshold.
(m) Notification of emergency
renovation operations.
(1) An emergency
notification must be submitted when the need for an emergency renovation
operation arises. A description of the sudden, unexpected event precipitating
the emergency renovation operation must be documented on the form. Notification
of an emergency renovation operation must be submitted as soon as possible, but
no later than the first working day after the date of the incident that
precipitates the emergency operation. Initial notification can be made by phone
followed by written notification, as required in subsection (d) of this
section.
(2) The building owner or
the delegated agent or the facility owner or operator, as applicable, must also
notify the appropriate DSHS regional office by phone and fax or email as soon
as possible, but no later than the first working day after the date of the
incident that precipitates the emergency renovation operation. The fax or email
must include a description of the emergency and a copy of the notification
form.
(n) Addition of
asbestos abatement or demolition to an existing notification. If asbestos
abatement or demolition is to be added to a notification and the notified
abatement or demolition stop date has not passed, a notification amendment must
be submitted to DSHS, as required in subsection (d) of this section to add the
asbestos abatement or demolition no fewer than 10 working days before the start
date of the added abatement or demolition.
(o) Notification of ordered demolitions for
structurally unsound buildings.
(1) If the
facility is being demolished under an order of a state or local government
agency or a court-issued order because the facility is structurally unsound and
in danger of imminent collapse, the DSHS notification must be submitted as soon
as possible, but no later than the first working day after the start date of
the demolition. The determination that a structure is in danger of imminent
collapse or that it is unsafe for anyone to enter must be made by a
professional engineer or government official reasonably qualified to make the
decision. A copy of the order must be attached to the notification form.
Notification must be made as required in subsection (d) of this section. If an
owner is unable to obtain a demolition order from a city, county, or state
government official and has a letter from a professional engineer stating that
the building is structurally unsound and in danger of imminent collapse, the
owner may contact DSHS to request a waiver from the 10 working day notification
deadline. Documentation supporting the inability to obtain an order must be
submitted with the waiver request.
(2) For structurally unsound buildings that
are in danger of imminent collapse, the building owner or the delegated agent
or the facility owner or operator must also notify the appropriate DSHS
regional office by phone and fax or email as soon as possible, but no later
than the first working day after the start date of the demolition. The email
must include a copy of the demolition order or letter from a professional
engineer, as applicable, and the notification form.
(p) Notification of asbestos abatement and
demolition. In a public building or a facility, including a commercial
building, when asbestos abatement and demolition are notified on the same
notification form and all asbestos abatement included in the notification
concludes early, the demolition may start as early as the next calendar day
when an amended notification is submitted, as required in the following
paragraphs. It is the responsibility of the person that submits the
notification to amend the abatement stop date and demolition start date.
(1) A statement must be included on the
initial notification submitted that demolition will start early if abatement
concludes early.
(2) An amended
notification must be submitted, as required in subsection (d) of this section
to DSHS as soon as possible, but no later than the new abatement stop
date.
(3) The appropriate DSHS
regional office must be provided with a fax or email copy of the amended notice
as soon as possible, but no later than the new abatement stop date.
(4) The appropriate DSHS regional office must
also be contacted by phone of the amended notice as soon as possible, but no
later than the new abatement stop date and demolition start date.
(q) Notification of a phased
project for asbestos abatement, demolition, or abatement and demolition in a
public building or facility.
(1) To qualify
as a phased project, the project must have planned periods of inactivity and
all of the abatement and demolition work must be performed at one site. The
site may contain more than one building, such as an office complex or
university, if the buildings are under the control of one owner or operator.
Notification of a phased project must not cover a period that exceeds 12
calendar months from the project start date. A completed Phased Project
Schedule form must be submitted with each notification. The notification form
must be submitted at least 10 working days before the start date of the first
phase. The notification form must be submitted, as required in subsection (d)
of this section.
(2) When there is
a change to the phased project schedule, the building owner or the delegated
agent or the facility owner or operator, as applicable, must:
(A) submit a notification amendment along
with the revised Phased Project Schedule form to DSHS as soon as possible, but
no later than the new proposed start date, stop date, or both of the phased
project, whichever is earlier; and
(B) also fax or email a revised Phased
Project Schedule form to the appropriate DSHS regional inspector as soon as
possible, but no later than the new proposed start date, stop date, or both of
the phased project, whichever is earlier.
(r) Asbestos notification fees.
(1) Applicability. The building owner or the
delegated agent or the facility owner or operator, as applicable, must pay to
DSHS an asbestos notification fee, as required in this subsection. The fee is
based upon the amount of asbestos removed and includes a subscription fee in an
amount determined by the Texas Department of Information Resources to recover
costs associated with the development and maintenance of Texas.gov services.
The subscription fee is 3% of the total notification fee. The minimum fee for
notification or the cancellation of a notification is $55.
(2) Payment.
(A) When a notification is submitted online,
the user has the option to pay the notification fee at the time of submission
or request to have an invoice mailed. DSHS mails an invoice to the building
owner or the delegated agent or the facility owner or operator, as applicable,
within 30 working days after the completion of the notified project. Payment
must be received by DSHS within 60 calendar days after the invoice
date.
(B) When a notification is
submitted by mail, DSHS mails an invoice to the building owner or the delegated
agent, or the facility owner or operator, as applicable, within 30 working days
after the completion of the notified project. Payment must be received by DSHS
within 60 calendar days after the invoice date.
(3) Notification fees.
(A) Fees for asbestos abatement projects.
(i) Notification fees for asbestos abatement
are based on the total amount of the RACM or ACBM reported on the notification
form to be abated, as required in § 296.191 of this chapter (relating to
Asbestos Management in a Public Building, Commercial Building, or Facility) and
this section. Fees for abatement are required to be paid based upon a $30 fee
for each asbestos reporting unit (ARU).
(ii) The minimum asbestos abatement
notification fee per notification is $55 and the maximum fee per notification
is $3,210 for abatement projects of 107 ARUs or more, except that the maximum
fee per notification for a school building is $320.
(iii) Notification fees are calculated by
measuring the amount of RACM or ACBM to be abated in square feet, linear feet,
or cubic feet.
(I) ARU calculation for square
feet. The number of ARUs is determined by measuring the total amount of RACM or
ACBM to be abated in square feet, dividing that number by 160, and, if
applicable, rounding that total down to a whole number.
(II) ARU calculation for linear feet. The
number of ARUs is determined by measuring the total amount of RACM or ACBM to
be abated from pipes in linear feet, dividing that number by 260, and, if
applicable, rounding that number down to a whole number.
(III) ARU calculation for cubic feet. The
number of ARUs is determined by measuring the total amount of RACM or ACBM to
be abated from off facility components where the length or area could not be
measured previously, dividing that number by 35, and, if applicable, rounding
that number down to a whole number.
(IV) Notification fee calculation. The
notification fee is calculated by adding the total number of ARUs for each
category (square feet, linear feet, and cubic feet) and multiplying the total
number of ARUs by $30.
(B) Fees for demolition only projects. The
fee per notification for demolition for which RACM or ACBM will not be abated
or will be left in place is $55.
(C) Fees for abatement and demolition
projects. The fee per notification for abatement with demolition is based
solely on the amount of RACM and ACBM removed during the abatement. If an
abatement notification is amended to add demolition, no additional fee is
required for adding the demolition to the notification.
(4) Reimbursement of notification fees. The
building owner or the delegated agent or the facility owner or operator, as
applicable, may submit a request for reimbursement based upon cancellation of
the abatement or demolition or overestimation in calculating the number of ARUs
of the amount of RACM or ACBM to be abated. If less than the reported amount
will be removed, a notification amendment must be provided to DSHS with the
reimbursement request. The written request must be received by DSHS within 10
working days after the notified project end date or its timely cancellation.
DSHS deducts an administrative fee of $57 from any reimbursement for an excess
payment of a notification fee. The requestor is not entitled to reimbursement
of a notification fee for $62 or less.
(5) Nonpayment of fees. Failure to pay the
required fee by the invoice due date is a violation under this chapter and may
subject the building owner or the delegated agent or the facility owner or
operator, as applicable, to an administrative penalty under § 296.318 of
this chapter (relating to Administrative Penalty).