Texas Administrative Code
Title 16 - ECONOMIC REGULATION
Part 4 - TEXAS DEPARTMENT OF LICENSING AND REGULATION
Chapter 70 - INDUSTRIALIZED HOUSING AND BUILDINGS
Section 70.21 - Registration of Design Review Agencies, Third Party Inspection Agencies and Inspectors, and Third Party Site Inspectors
Current through Reg. 50, No. 13; March 28, 2025
(a) Pursuant to the criteria established by the council as set forth in §§ 70.22, 70.23, and 70.24 the executive director will recommend qualified design review agencies, third party inspection agencies, third party inspectors, and third party site inspectors to the council for approval. An application for approval shall be submitted in writing to the executive director for consideration and recommendation to the council.
(b) If the application is approved by the council, it shall be filed with the department as the registration of the applicant as a design review agency, a third party inspection agency, a third party inspector, or a third party site inspector to perform specific functions. The department shall issue a certificate of registration that shall state the specific functions that the registrant is approved to perform. The certificate of registration shall be valid for a 12-month period. This registration shall be a continuous registration so long as:
(c) Design review agencies, third party inspection agencies, third party inspectors, and third party site inspectors shall notify the department in writing within 10 days if:
(d) An application for original registration or renewal may be rejected if any information contained on, or submitted with, the application is incorrect or incomplete. The certificate of registration may be revoked or suspended or a penalty or fine may be imposed for any violation of Chapter 1202, the rules and regulations in this chapter or administrative orders of the department, or the instructions and determinations of the council in accordance with § 70.90 and § 70.92.
(e) If a third party site inspector, third party inspector, third party inspection agency, or design review agency is not approved, the department shall forward a written explanation to the applicant setting forth the council's reasons for the disapproval and that the applicant may request an administrative hearing to determine if the application should be denied.