Texas Administrative Code
Title 16 - ECONOMIC REGULATION
Part 2 - PUBLIC UTILITY COMMISSION OF TEXAS
Chapter 25 - SUBSTANTIVE RULES APPLICABLE TO ELECTRIC SERVICE PROVIDERS
Subchapter I - TRANSMISSION AND DISTRIBUTION
Division 1 - OPEN-ACCESS COMPARABLE TRANSMISSION SERVICE FOR ELECTRIC UTILITIES IN THE ELECTRIC RELIABILITY COUNCIL OF TEXAS
Section 25.199 - Transmission Planning, Licensing and Cost - Recovery for Utilities within the Electric Reliability Council of Texas
Current through Reg. 50, No. 13; March 28, 2025
(a) Purpose. The purpose of this section is to prescribe the procedures and criteria under which the commission may require an electric utility or a transmission and distribution utility to construct or enlarge facilities to ensure safe, reliable service and to reduce transmission constraints within the Electric Reliability Council of Texas (ERCOT) in a cost-effective manner.
(b) Applicability. This section applies to all electric utilities, transmission and distribution utilities and ERCOT. This section does not apply to an electric utility or transmission and distribution utility located outside of the ERCOT region. For the purpose of this section, an electric utility includes a municipally-owned utility and an electric cooperative.
(c) Eligibility for filing a request under this section. Any interested party in the ERCOT electric market may file a request for an order under this section.
(d) Filing requirements. Sections 22.251(d) - (f) of this title (relating to Review of ERCOT Conduct) shall apply to proceedings under this section, except as otherwise provided. In accordance with § 22.251(f) of this title, ERCOT shall file a response to the application within 14 days after it receives the notice required under subsection (g) of this section. ERCOT shall include as part of the response all existing, non-privileged documents that support ERCOT's position on the issues identified by the applicant.
(e) Standard for review. The commission may require an electric utility or a transmission and distribution utility to construct or enlarge transmission facilities to ensure safe and reliable service for the state's electric markets and to reduce transmission constraints within ERCOT in a cost-effective manner where the constraints are such that they are not being resolved through Chapter 37 or the ERCOT transmission planning process. An applicant bears the burden of persuading the commission that the facilities are necessary to ensure safe and reliable service for the state's electric markets or to reduce transmission constraints within ERCOT in a cost-effective manner.
(f) Threshold requirements. In its request, the applicant must plead facts that are sufficient, if proven, to show that the request is likely to be granted under the standards of this section.
(g) Notice. An applicant shall serve copies of its complaint and other documents, in accordance with § 22.74 of this title (relating to Service of Pleadings and Documents), and in particular shall serve a copy of the complaint on ERCOT's General Counsel, every other entity from whom relief is sought, the Office of Public Utility Counsel, and any other party as may be appropriate. The notice required by ERCOT under § 22.251(e) of this title shall also be provided to all transmission service providers in ERCOT.
(h) Cost effectiveness. Prior to granting a request filed pursuant to this section, the commission, together with the applicant or other parties as appropriate, may undertake a comprehensive cost-benefit analysis to consider both quantitative and qualitative costs and benefits of the proposed facilities. The analysis should consider at a minimum:
(i) Commission order. If the commission concludes that the applicant has demonstrated that the facilities are needed to ensure safe and reliable service for the state's electric markets or to reduce transmission constraints within ERCOT in a cost-effective manner and that the constraints are not being resolved through Chapter 37 or the ERCOT transmission planning process, it shall order an electric or transmission and distribution utility or utilities to construct or enlarge the requested facilities.