Section 25.83 - Transmission Construction Reports
Current through Reg. 50, No. 13; March 28, 2025
(a) General. Each electric utility constructing a facility that requires reporting to the commission under § 25.101 of this title (relating to Certification Criteria) shall file the reports on the commission-prescribed forms. The commission may require additional facts or information other than those required in commission forms or this section. Nothing in this section should be construed as a limitation of the commission's authority as set forth in the Public Utility Regulatory Act. All reports required in this section shall be filed in a project established by the commission. Projects that shall be reported include:
(b) Reporting of projects that require a certificate. Projects that require a CCN under § 25.101(b)(3) of this title shall be included in the next scheduled monthly construction progress report following the filing of a CCN application and in all subsequent construction progress reports until the final project costs have been reported.
(c) Reporting of projects not requiring a certificate. The following information is required to be reported for projects that do not require a CCN under § 25.101(c)(5) of this title.
(d) Reporting requirements for emergency projects. The repair or reconstruction of a transmission facility due to emergency situations shall proceed without delay or prior approval of the commission. When emergency repairs with estimated costs exceeding $250,000 have been performed and power has been restored, the affected utility shall file a report describing the work performed and the estimated associated costs. This information shall be included as a project reported in a regularly scheduled construction progress report within 45 days of the completion of the repair and in all subsequent construction progress reports until the final costs have been reported.